Wetlands Treat Area Runoff at Urban Lake Restoration

Text size: A A

Best Water/Environment Project, Southern California: Echo Park Lake Rehabilitation, Los Angeles

Photos by Gary Leonard Studio
Thanks to this $26.3-million project, the watershed has been remediated to help the city meet Clean Water Act mandates while maintaining flood control functions and enhancing the Los Angeles River Watershed.
----- Advertising -----

The Echo Park Lake Rehabilitation brought back to life a historic watershed in the heart of Los Angeles. The lake began as a drinking water reservoir in the 1860s and eventually became a flood control basin and recreation area. Thanks to this $26.3-million project, the watershed has been remediated to help the city meet Clean Water Act mandates while maintaining flood control functions and enhancing the Los Angeles River Watershed.

The rehabilitation routes all upstream dry weather urban runoff, and 25% from wet weather, from 769 acres of urbanized watershed through the lake to be treated by hydro-dynamic separators and various constructed or restored wetlands. This offers the additional benefit of providing wildlife habitat at the lake. Construction also included an automated aeration system and adjustable outlet weir.

Prior to the rehabilitation, exfiltration through the retaining walls and basin required significant potable water to keep the lake full. To minimize water loss, an innovative liner system was added that uses native clays found on site that have been reconditioned with naturally occurring bentonite. One Best Projects judge praised the team for designing this cost-effective, creative and sustainable solution, rather than using synthetic liners.

During construction, the project site needed to remain available for use as a storm detention basin. Through partitioning, creating bypassing flows and benefiting from a dry winter, the team was able to complete the project on schedule and under the original cost estimate. Formal partnering sessions required by the owner throughout the construction phase helped to create a unified team and resolve any disputes quickly.

Judges remarked that instead of seeing an impaired body of water, visitors will now find much to enjoy with the park's many enhancements, including improvements to the lake's iconic fountain, a new boardwalk displaying educational signage and reestablishment of the lake's 1920s Chinese lotus beds. The lotus plants help to boost water quality while serving an integral role in the local community's annual Lotus Festival.

Key Players

Contractor Ford E.C. Inc., Los Angeles

Owner City of Los Angeles Bureau of Engineering

Lead Design Black & Veatch, Los Angeles

Civil Engineer Brown & Caldwell, Los Angeles

Landscape Architect AECOM, Los Angeles

Geotechnical Engineer Ninyo & Moore, Irvine

Consultants Brinkerhoff & Associates, Fallbrook; Coast Surveying, Tustin; E2 Consulting Engineers, Emeryville

Keywords:

----- Advertising -----
New Blog: Vertically Speaking in Northern California
New Blog: Field Notes
Reader Photos
Photos from California Construction Photo Showcase
Dodge Lead Center
Search for local construction projects OR CALL 877-234-4246 and get a FREE Lead Now!
Search by Project Type & State





----- Advertising -----
 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.