|
Luxury Living, San Jose Style
City's first high rise condo project
sees May completion
By Don Lipper & Elizabeth Sagehorn
To paraphrase "The Jeffersons" theme song, San
Jose is moving on up to the big time, with some deluxe apartments
in the sky.
The
$50-million City Heights at Pellier Park project is the first
high rise condominium building to open its doors in San Jose.
The 124 luxury condos are appointed with smooth wall finishes,
granite countertops, cherry wood cabinets, imported ceramic
tile, upgraded appliances, nine- to 11-ft ceilings, generous
bedrooms and closet spaces. Each room has bundled Cat5 cabling,
plus the choice of cable or two satellite systems. The bathrooms
have designer plumbing and light fixtures.
The Developer/Owners are Green Valley Corporation and City
Heights LLC. The general contractor is Barry Swenson Builder
with designs from architects The Steinberg Group and Berger,
Detmer, Ennis.
After Steinberg Architects furnished the design, the architects
of record, Berger, Detmer, Ennis, ushered the project from
drawings through construction. "We wanted to have a very
good design, make it an iconic type of building for San Jose,"
says Chad Zane, project manager for Berger, Detmer, Ennis.
The exterior finish system was glass fiber reinforced concrete
panel, so there was a high level of accuracy required to determine
openings sizes for windows, according to Zane, who adds that
the benefit of GFRC is that it allows economies of scale where
repetitious panels can be poured from the same mold. Construction
is very fast with crews constructing a floor a day, he adds.
The downside is that unlike low-rise construction, change
orders on the exterior could cause a nightmare.
"Things couldn't be changed in the process," says
Zane. "The plan wasn't set in stone, but it was set in
GFRC."
During the construction stage, access to the infill site
presented the biggest challenge to Barry Swenson Builder.
Most of the hard work took place before workers ever got to
the site.
Because of the access limitations of the site, which included
one-way traffic on two sides, a firehouse on the other and
the fourth side landlocked, "[we] spent a lot of time
orchestrating the sequencing of events, from bringing materials
to scheduling pours," says Steve Andrews, vice president/project
manager of City Heights Construction for Barry Swenson Builder.
"Vertical transportation of materials is much more acute
in high rise because the configuration is a much denser unit
count (124 units) per acre. The sequencing and the safety
awareness has to be more thorough."
Everything needed a higher level of planning, from the mat
foundation through the skin system up to the newly designed
roof features. "You're worried about waterproofing details,
wind, seismic loads on exteriors. Your skin system becomes
much more heavy duty than low rise applications," says
Andrews.
The design turned the roof into an architectural element.
The original design of the roof had a tipped roof that enclosed
a mechanical penthouse level. The team decided to make the
roof lighter and more dynamic. Now it is capped with an outrigger
trellis and blades. The light and shadows continuously play
across the top of the building as the sun moves across the
sky.
"The change resulted in a functional and aesthetic improvement
for issues like window washing equipment clearance, a lot
of mechanical issues like venting, etc." says Zane.
The project is nearly completed. At press time sheet rocking
was still being done, but everything looks on track for a
May 1 move-in date.
The Project Team
Owner/developer: Green
Valley Corp., and City Heights LLC, San Jose
General Contractor: Barry
Swenson Builder, San Jose
Architects: The Steinberg
Group, San Jose office; and Berger, Detmer, Ennis Architects,
San Francisco
More March Newswatch items...
Skyline Identity
|