|
Bigge Crane & Rigging Uses Alternative
Lifting Technology in Bay Bridge Project Phase
By Robert Carlsen
SAN FRANCISCO--Construction of the new
San Francisco Oakland Bay Bridge reached a milestone at press
time when the first transition span, linking the concrete
Skyway bridge deck section with the yet-to-be-built suspension
bridge, was being lifted into place using trail-blazing alternative
lifting technology.
Specialist
heavy lifting contractor Bigge Crane & Rigging of San
Leandro is using computer-controlled Hydrospex strand jacks
to precision lift the 2,000-ton steel span off a barge to
a height of approximately 200 ft. within tolerances of 1/32
of an inch.
Although strand jacks are not new technology, they have never
been used on this scale before in bridge construction in the
United States, said Pete Ashton, Bigge's vice president of
major projects.
At the Oakland side (to the east), where the Skyway bridge
deck has already been constructed, the strand jacks will be
mounted on a mobile jacking platform that will be supported
by a pair of 60-ft. girders, cantilevered 28 ft. off the bridge
deck.
At the San Francisco side (to the west), main contracting
consortium Kiewit-FCI-Manson has constructed two steel lifting
towers, founded on piles driven into the bay for this purpose.
Bigge will furnish two girders that span 125 ft. across the
top of this lifting tower and strand jacks will be mounted
on top of a mobile jacking platform that sits on the girders.
Both of Bigge's jacking platforms are capable of synchronized
8-in. longitudinal and transverse movement.
At the Oakland end, Bigge is using four strand jacks, each
of which has a lifting capacity of 365 tons. Each jack pulls
on a bundle of 31 strands. Each rope is 0.62 in. in diameter.
At the San Francisco end, six jacks of 235-ton lifting capacity
will be used. These jacks have 19 wire rope strands, each
0.62 inches in diameter.
All of the jacks are synchronized for simultaneous operation
and load control within a 1/32 inch.
"No traditional crane, particularly a barge-mounted
one on the water, could do this job with the required combination
of lifting capacity and precision," said Ashton.
Ashton added that this is the first major project on which
Bigge has used its new strand jack equipment since becoming
the exclusive representative of Hydrospex, the Dutch manufacturer
that also supplied the strand jack technology that raised
the sunken Russian Kursk submarine in 2002.
The second transition span, parallel to the first, to carry
the westbound carriageway, is scheduled to be lifted into
place in June.
Each lift will take approximately 10 hours, as the strand
jacks raise the load at speeds of up to 30 ft. per hour. During
the lifts the tubs, as these transition spans are called,
will be maintained with an eighth of an inch of the required
attitude. Given that the tubs are 200 ft. long by 85 ft. wide,
this can only be achieved by computerised monitoring, said
Ashton.
On each lift, once the tub is lifted to elevation, a temporary
support tower will be skidded under the tub for support until
the concrete joint with the existing Skyway is poured and
cured, filling a gap of some 6 ft. The San Francisco (west)
end of the tub will be supported by another temporary tower
until the suspension bridge is constructed. When each of these
towers is skidded into position, Bigge will lower the tub
onto the towers and adjust the tub for the exact cross fall
and longitudinal elevation. After the tub is secured to the
temporary support towers, the San Francisco end lift system
will be dismantled. The Oakland end will be left in position
three months while the concrete closure pour cures.
Bigge is also contracted to load the tubs onto a barge in
Portland, where they have been fabricated, and ship them to
the site. The first one was loaded onto the barge on Dec.
29 using 48 axle lines of Scheuerle self-propelled hydraulic
modular trailer (SPMT). The barge was then towed out of the
mouth of the Columbia River to the Pacific Ocean, where it
followed along the coast line to San Francisco Bay, traveling
under the Golden Gate Bridge to the site wharf in Oakland.
"Transporting and lifting such a super-heavy load to
such a height is a significant operation," said Weston
Settlemier, president of Bigge Crane & Rigging. "We
are unaware of such a heavy load ever being lifted so high
anywhere in the United States. However, we have engineered
a solution, using our own equipment, which is the very latest
in computer-controlled lifting technology that makes this
job possible."
|