|
A Whole-Lotta Lead
Stanford Cancer Center Is
Loaded With the Material
By Richard Horgan
|
|
|
The $85 million
Center for Cancer Treatment and Prevention at Stanford
University includes 80 exam rooms, 50 chemotherapy stations
and a radiation therapy suite. The Ambulatory Care Pavilion
on the top floor of the three-story, 218,000-sq.-ft.
structure will focus on outpatient surgery.
(photo courtesy of Bob Swanson
Images)
|
More than 10 years after Stanford University first conceived
the idea of grouping all resources for diagnosing and treating
cancer patients under one roof, a new $85 million facility
completed Dec. 31 is finally set to open next month.
The Center for Cancer Treatment and Prevention includes 80
exam rooms, 50 chemotherapy stations and a radiation therapy
suite, while the Ambulatory Care Pavilion on the top floor
of the three-story, 218,000-sq.-ft. structure will focus on
outpatient surgery.
The endeavor marks the latest triumph in the health-care
field for Foster City-based general contractor Rudolph and
Sletten. The family-owned business has also been involved
in medical projects such as the adjacent Lucille Packard Children's
Hospital at Stanford; Kaiser Permanente in Fremont, Santa
Clara and Roseville; and Children's Hospital in Los Angeles.
"Rudolph and Sletten's team demonstrated an extreme
propensity to detail and proactive planning, which translated
across the budgeting and scheduling," said John Gaston,
project manager for Stanford. "With their assistance,
we were able to trim more than 5 percent of the construction
budget without adversely impacting the project's functionality
or aesthetics."
One of the biggest challenges for Rudolph and Sletten and
Lone Star Construction Co., a Houston, Texas-based subcontractor,
was the facility's basement, which houses seven machines known
as "linear accelerators" that use electricity to
form streams of fast-moving atomic particles to treat cancer
patients.
Each machine is housed in a separate vault and required more
than 200,000 lbs. of lead bricks on the walls, ceilings and
decks above to act as a radiation shielding system. Their
encasement is fortified by a concrete wall up to 4 ft., 11
in. thick, a maze wall design and 10 ft. of soil outside each
vault.
The lead itself was cut within a specially constructed booth
equipped with filters and a continuous exhaust to remove lead
particles from the shed and clean the air before it was emitted
into the atmosphere. The air inside and outside the linear
accelerator rooms was continuously monitored during the two-year
construction phase to monitor particulate levels.
"Safety associated with lead installation was addressed
for all workers onsite as well as the general public,"
said Marcus Staniford, project executive for Rudolph and Sletten.
"It was of paramount importance to address the safety
considerations of the entire lead-shielding process, from
air cleanliness to material handling, cutting and installation."
The building's foundation system, which includes spread footings,
mat slabs and grade beams, was designed to respond to the
extreme building loads of 1.6 million lbs. of lead and large
lateral design loads associated with the linear accelerator
vault walls.
Additionally, because university-occupied buildings surrounded
the construction site on all sides, some of the work had to
be performed at night.
"We had to use both a 300-ton crane with a 180-ft. Luffer
and a 280-ton boom and gib crane due to limited access around
the perimeter of the building," Staniford said.
|
|
|
Seven cancer
treatment machines-known as linear accelerators, will
be housed in separate vaults that require a radiation
shielding system made up of more than 200,000 lbs. of
lead bricks on the walls, ceilings and decks. Their
encasement is fortified by a concrete wall up to 4 ft-,
11-in. thick, a maze wall design and 10 ft. of soil
outside each vault .
(photo courtesy of Bob Swanson
Images)
|
To accommodate installation of about 300 precast concrete
panels ranging in size from 4 to 32 ft. wide, workers had
to utilize a crane that could reach from one side of the building
to the other since access was limited on three sides of the
structure, Staniford added.
While shielding is often done with just concrete, Rudolph
and Sletten used a combination of concrete and lead because
of limited space on the construction site. Specifically, 8
in. of lead were added to the nearly 5-ft.-thick concrete
walls.
The firm also worked closely with a radiation shielding consultant
and physicist, Nisy Elizabeth Ipe, to prevent any escape of
secondary emissions from the linear accelerator's powerful
radiation beam, which targets a patient at specifically calculated
angles.
"As a physicist, I can design the shielding, but if
there is no follow-through by the contractor, I have no guarantee
that what I designed is what was built," Ipe said. "Rudolph
and Sletten were very conscientious about follow-through and
making sure that everything [was] done correctly."
Like Rudolph and Sletten, Los Angeles project architects
Michael Bobrow and Julia Thomas have carved out a solid reputation
in the health care field. Their design for the Stanford cancer
center was honored by the Chicago-based trade weekly Modern
Healthcare for its "patient-focused care," while
their previous work on Inpatient Care Units merits a major
section in the Wiley Books publication "Healthcare Facilities."
|