|
Artfully Merging Old With New in
Sacramento
Restoration and Addition for City
Hall Is Well Under Way
By Cory Golden
 |
|
Restoration
of the historic clock tower, including cleaning and
resealing the copper dome, was completed in the fall.
photo by Cory Golden
|
Crews excavating a 170-space subterranean parking garage
for the Sacramento City Hall project last April found what
turned out to be 8,000-year-old artifacts and human remains.
Construction stopped, and archaeologists took over.
American Indians negotiated with the city, making sure that
at least some of what was found received a proper burial.
It wasn't until after a 10-week, $4 million delay ($2.3 million
covered the costs of the archaeologist's contract) that work
fully resumed in July on the $85 million restoration of the
93-year-old City Hall and the construction of an adjacent
200,000-sq.-ft. building to house the office of the mayor
and other city officials. The general contractor, the San
Jose office of Hensel Phelps Construction Co., expects to
complete the project in about 12 months.
"I've never had a site that had Native American artifacts,"
said development manager Elle Warner of Sacramento-based David
S. Taylor Interests Inc. "A lot of us had never had that
experience. It's been both a trial and frustration, but it's
also been a revelation to know that the site years ago was
a center of the community. Now that we're past the worst of
it, I think there's something kind of noble about that."
When almond-colored precast concrete, stone and brick flesh
out the new building, the difference between the old City
Hall and its new annex will not be jarring, especially from
ground level.
When completed, the entire City Hall complex will consolidate
city functions, eliminating the need for leased office space.
The existing building is being renovated for the first time
and given seismic, mechanical and electrical upgrades.
To compliment the three-story, 38,900-sq.-ft. historic structure,
the new building is being erected slightly down slope and
will stand just five-stories tall.
Design work, which incorporated public feedback, began on
the project in 2000. Planners worked to create a flowing,
functional complex with high-level finishes while not overwhelming
an iconic structure, said Bryan Amarel, Hensel Phelps project
manager.
|
|
|
Rendering of the
200,000-sq.-ft. addition to the existing Sacramento
City Hall
|
The Sacramento office of Fentress Bradburn is the exterior
design architect. The Sacramento office of Chong Partners
Architecture is both the renovation architect on the historic
building and interior design architect on the new one. Outside
work on the historic building includes repairing ornamentation,
brick work, windows and sheet metal flashing, as well as roof
replacement. Walls will be repainted, sealed and caulked.
Corroded structural reinforcements and wood will be replaced.
Openings made to connect the City Hall with an annex in 1939
will be filled to match the original design.
Inside, the building's public spaces are being spruced up
to match their original luster, while offices are being remodeled
to better accommodate the city treasurer, city clerk and other
functions.
Just to the north, the new building's curved façade
will overlook a centrally located plaza.
The entryway of the new building will feature a floor of
stone cut in an elliptical shape by Los Angeles-based Italian
Marble Inc., the colors weaving basket-like around the city
seal. Past it will be the new home of the mayor, City Council
members, city manager, city attorney, public works, planning
and other offices.
Site preparation included the demolition of three adjoining
structures, including the annex. For the duration of construction,
the mayor's, city manager and City Council's offices have
been moved, along with some other functions.
Restoration of the historic clock tower, including cleaning
and resealing the copper dome, was completed in the fall.
Now, erection of the new building's 1,700 tons structural
steel is under way. When this phase is complete, crews will
also have used 690 tons of reinforcing steel and 10,000 cu.
yds. of concrete.
"We took a building that was a fabulous treasure, [but
where] the exterior sheet metal [trim] was looking shabby
and the terra cotta was cracked, and now it's just going to
sparkle," Warner said. "And we've added a building
that will give a dignified and sophisticated backdrop to this
little jewel."
|
The Development Team
Developer: David
S. Taylor Interests Inc.
General Contractor:
Hensel Phelps Construction Co.
Architects: Fentress
Bradburn (exterior design architect). Chong Partners
Architecture (renovation architect on the historic building
and interior design architect on the new one).
Major subcontractors:
Herrick Steel
Airco Mechanical
Rex Moore Electrical
Burnett and Sons Windows and Custom Millwork
J.W. McClenahan
Peninsula Builders
Giampolini/Courtney Masonry Restoration and Waterproofing
|
|