|
What a Site
Project Team Overcomes High School's
Hilly, Compact Location
By Greg Aragon
In
60 days, when many schools are preparing to close their doors
for summer vacation, the portal of San Marcos' new $53 million
Mission Hills High School is scheduled to open for the first
time.
The 275,000-sq.-ft. learning center-the city's second high
school-will welcome administrators and faculty a couple of
months before students arrive in late August. The new school
will gradually siphon off the overcrowded population from
San Marcos High, which currently is packed with an enrollment
of 3,200, about 700 over the ideal capacity.
The project, which broke ground on March 1, 2002, is currently
in the punch-list stage, and construction crews are wrapping
up the installation of the athletic field's artificial turf.
Topographical issues were at the top of the tough-task list
for the school's design and construction team.
"Fitting a comprehensive, 2,400-student high school
onto a 42-acre site is extremely complicated," said Jon
Baker, president and CEO of the project architect, Glendora-based
NTD. "Schools this big are usually built on at least
65 acres."
To overcome the tight site, Baker said the school was designed
with the buildings terraced into the north San Diego County
hillside.
"The key was developing different pad elevations that
allow good circulation flow as well ADA compliance,"
Baker said. "Even though it's a complicated hillside
site, we still have to meet [ADA] requirements and try to
avoid making the campus look like a nursing home with ramps
and rails everyplace."
In a major effort to make the site fit for construction,
San Marcos-based Lusardi Construction Co., the general contractor,
built a 40,000-sq.-ft. modular retaining wall and blasted
approximately 400,000 cu. yds. of rock to create the school's
building pads.
Jeff Jenco, a Lusardi vice president, said the hilly site's
70-ft. elevation variance created difficulties regarding ADA
requirements for maximum slope for sidewalks and building
separations.
Jenco, whose company moved 1 million cu. yds. of soil during
construction, said crews solved the slope problem by "selectively
grading the project and creating a hole where we could bury
large rocks generated from the blasting.
"We used retaining walls to create specific pad elevations
that could be graded and held consistent, then used the athletic
fields as our balance, because they could be raised or lowered
to allow for the variance that we incurred due to footings,
utility and trenching spoils."
Good Until the Cows Come Home
Besides campus size and slope, the school's location was
also cause for concern: it was built on the pasture area of
an old dairy farm.
Thom Clark, director of facilities for San Marcos Unified
School District, said that obtaining approvals from the state
department of toxic substance control wasn't a piece of cake.
"We had to go through a 'preliminary danger agreement'
and it took about an extra year out of our schedule"
to process the paperwork affirming that the site was safe
to build on, he said. "We had to prove through soil testing
that there weren't any hidden methane issues."
When complete, Mission Hills High School will feature 11
two-story buildings, a quadrangle and parking for up to 1,200
cars. It will include a 2,600-seat football stadium with concrete
bleachers, synthetic turf field, rubber track and full support
amenities; gymnasium; baseball and softball fields; two soccer
fields; 10 outdoor basketball courts; and 10 outdoor tennis
courts.
Lusardi also installed three traffic signals in front of
the school.
In the fall, Mission Hills High will welcome about 1,200
ninth-, 10th-, and 11th-graders. It will grow to about 1,600
students when seniors are added in the 2005-06 school year.
|