|
Ready for the Digital Age
Major Upgrades Improve Caltrain Service
and Operations
Approximately $115 million has
been spent to upgrade tracks, add three stations and implement
new technology to the 44-mi. commuter railroad between San
Francisco and San Jose. The construction coordinator for the
general contracting team called the project "more extensive
than any other project" he has worked on. Construction
will be completed this month. Express service begins this
summer.
By Thomas York
Passenger trains have linked San Francisco and San Jose for
more than 140 years. In fact, the 44-mi. Caltrain system is
one of the oldest mass transit operations in the West.
 |
| Lawrence is the location of one of three new stations
recently built for project owner Caltrain. The others
are in Bayshore and Millbrae (photo by Thomas York). |
The system now has been improved with a $115 million upgrade
by joint-venture partners St. Joseph, Mo.-based Herzog Construction
Corp. and Alameda-based Stacy and Witbeck Inc. that will improve
service and allow Caltrain officials to add limited express
service beginning this summer.
The two-year-long project replaces block-system train control
technology with a digital central train control system. Three
new stations were built-at Bayshore near San Francisco, in
Millbrae (with connections to Bay Area Rapid Transit) and
in Lawrence near San Jose in the Silicon Valley.
Contractors also replaced much of the existing 50-year-old
track (with continuous welded rail and concrete ties) from
Menlo Park south to San Jose and built 4 mi. of new track
and three crossovers to allow faster trains to bypass slower
ones.
A week's worth of work on the weekend
Most of the work was undertaken on weekends, when trains were
halted to allow workers to swarm the tracks. What workers
accomplished was just short of amazing, given the size and
complexity of the project.
"It was a very, very aggressive schedule from the get-go,
and we knew it would be very difficult to complete on time,"
said Juston Poeling, construction coordinator for Herzog/Stacey
and Witbeck. "The level of planning was much more extensive
than any other project that I have worked on."
He said crews from the two contractors planned a week's worth
of work on Sunday for the following week, and then met again
Thursday morning and Thursday afternoon to go over last minute
changes and other details.
The test of their organizational abilities came at 4 a.m.
on Mondays. That's when each weekend's worth of work had to
be completed in compliance with all of Caltrain's operating
rules and regulations, Poeling added.
"It's a very active railroad-you just don't go and build
track," he said.
Paul Loukianoff, project manager for CTX South, agreed that
the job took extraordinary planning and a furious work pace.
At the height of the project, CTX South crews were replacing
an average of 6,000 lin. ft. of track and ties each weekend.
Loukianoff estimated that $1 million was spent every weekend
on this portion of the overall project, or more than $54 million
in approximately 52 weeks.
"We had 150 people on the south end of the project,
and the subs had another 200 people," said Loukianoff,
who also worked on Santa Clara County's Vasona light-rail
extension before managing the Caltrain project. "Based
on my experience from other projects, that was a lot of people
to have on a job."
Nesting birds took priority
Patrick Gray, project manager for CTX North, said some of
his projects required close coordination with outside agencies
that sponsored the upgrade. For example, while rebuilding
a small bridge in South San Francisco, crews had to work around
environmental restrictions set down by the California Department
of Fish & Game.
The agency put his crews on a strict construction timetable
to better protect fish and birds nesting nearby. The crews
had to construct the bridge in "halves" from April
to October 2003, shifting trains to track on one side of the
crossing while working on the other side of the bridge.
"It was very tight," Gray said. "We had to
get in and get out knowing that if we didn't get the bridge
completed by a certain date we'd have to wait a whole new
season." he added. "It looks like a simple bridge,
but it wasn't simple to build."
Crews worked even while trains were in service on Thursdays
and Fridays, which required added safety measures, including
a flagman, to warn crews when trains approached.
The bridge construction included pouring of reinforced concrete
abutments, foundations and piers, then driving support piles
and laying down pre-cast beams to accommodate the track deck.
The entire project started in June 2002 and is expected to
be completed this month. Meanwhile, the new central train
control system, or CTC, will allow dispatchers to control
trains from a centralized office. For example, controllers
will be able to route faster trains around slower trains where
the system has now been double-tracked.
The San Leandro office of Amelco Electric Inc. served as the
electrical subcontractor for the CTC installation.
Dave Martens, project manager for Amelco, said fielding and
managing two different installation crews, one for the north
and one for the south, was difficult. At the height of the
installation, he was managing more than 100 workers.
The crews included unionized laborers from the Brotherhood
of Railroad Signalmen, who did most of the physical installations,
such as digging new trenches for cable and installing new
signal boxes, and signal engineers and technicians from San
Leandro-based subcontractor B&C Transit Consultants Inc.,
which did the installation and testing.
The CTC was installed and tested in segments. "I learned
quite a lot in the process," Martens said. "It was
fairly complicated, and it didn't turn out as easy as we thought
it would."
Caltrain spokesperson Jayme Kunz said the project was about
three months behind the original schedule, a delay in large
part due to the complexities of installing and testing the
new CTC system.
"The signal system is a critical safety element, and
we have to make sure that the signaling service is in place
and operating safely," she said.
Nevertheless, Kunz said one added advantage to the new CTC
system is that it will allow Caltrain to run trains on single
portions of track and bypass repair and maintenance work.
With CTC in place and operational by next month, Caltrain
won't have to shut down train service like it has for the
past two years.
"We'll probably never have to do this again," Kunz
added.
|