|
Largest Medical Center in the Silicon Valley
First Half of Kaiser Project 'All But Completed'
Oakland-based Kaiser Permanente
said a 520,000-sq.-ft. medical office building in Santa Clara
will be substantially completed in the fall. It is the first
major component of a 1.2 million-sq.-ft. medical center complex.
The entire 37-acre project will be completed in 2007.
By Thomas York
The first half of Kaiser Permanente's $375 million, 1.2-million-sq.-ft.
Santa Clara Medical Center is moving towards "substantial
completion in November," said Michael Stoops, the health-care
system's project manager. "It's all but completed at
this juncture."
 |
| The second phase of construction
now under way includes a 327-bed hospital that will double
the number of beds in the existing facility on Kiely Boulevard
(photo by Thomas York). |
The work involves construction of a four-story, 520,000-sq.-ft.
medical office building at the corner of Lawrence Expressway
and Homestead Road. The entire project began in October 2001.
Stoops said the HVAC and electrical connections need to be
made before the office building can be finished and then occupied,
a step that hinges upon completion of a four-story, on-site
utility plant.
San Francisco-based Anshen+Allen Architects is the designer
for the entire project.
Stoops said the medical office building will be occupied in
August 2005, while the diagnostic and other buildings will
be completed in August 2006. The hospital wing is scheduled
to open in 2007.
The 37-acre project is the second-largest hospital construction
effort in the state and-the largest in Silicon Valley. It
is the largest project in the Kaiser system, Stoops said.
Meanwhile, crews from the general contractor, Foster City-based
Rudloph and Sletten, continue building the second half of
the complex, a 327-bed hospital that will double the number
of beds in the existing facility on Kiely Boulevard.
Colossal crane used
Hayward-based Marelich Mechanical brought in a 600-ton, 30-story-tall
crane-the largest hydraulic crane west of the Mississippi
River-to pick and place 23,000-lb. HVAC units to the roof
of the hospital in December.
"Our use was part of the incentive for Bigge [Crane
& Rigging Co.] to bring it out to the West Coast,"
said Chad Johnston, Marelich Mechanical's project manager
on the Kaiser Santa Clara job. Johnston said the "picks"
took four days to complete.
The German-made crane was dissembled into 43 pieces in New
Jersey and then shipped to Oakland. The pieces were then trucked
to the Santa Clara site and re-assembled over a one-week period.
The crane took only four days to lift the HVAC equipment into
position.
Despite its weight and size, Johnston said the crane was
easy to maneuver, once it was brought to the site and assembled.
"Except for the counterweights, you could drive it down
the road," he added with a wide grin. "It went real
smooth and there were no problems."
Crews began putting in place the first of 190-plus 23,000-lb.
steel columns for the new four-story hospital in January.
The columns were to be in place in May and welding completed
in June.
 |
| The 37-acre project is the second-largest
hospital construction effort in the state and the largest
in the Silicon Valley (photo by Thomas York). |
The steelwork includes the installation of Japanese-made
unbonded braces to protect the hospital against major earthquakes.
Structural engineer Arup of California provided the idea
to use the braces, which act something like automobile shock
absorbers during a temblor.
Once the structural steel work is completed, work will then
shift to the decking, exterior plaster and window wall systems
and roofing.
Kaiser is also constructing two new concrete parking structures
at the site; one a four-story structure designed to accommodate
1,470 cars. Overall, the two structures will provide parking
for more than 3,200 automobiles.
|