|
Feet to the Fire in Fresno
Matt Seals Cuts Teeth on Major St. Agnes
Expansion
The project manager for Visalia-based
Seals/Biehle General Contractors inherited a stalled segment
of a major expansion of St. Agnes Medical Center in Fresno.
Seals said keeping the trades focused on the schedule will
result in a late-November delivery of the expansion's largest
component, a 232,000-sq.-ft. heart and vascular department.
By Paul Napolitano
Five years removed from the tranquil college life at Cal
Poly San Luis Obispo, Matt Seals, the project manager for
Seals/Biehle General Contractors of Visalia, has the task
of keeping a formerly maligned project on schedule.
 |
| PHOTO COURTESY OF SEALS/BIEHLE GENERAL
CONTRACTORS. |
Seals' project, the $100 million expansion of St. Agnes Medical
Center in north Fresno, will nearly double the 250,000-sq.-ft.
hospital.
The Office of Statewide Health & Planning Development
last summer halted construction of the three-phase project,
which began in 2000 and was scheduled for completion in December
2003.
The initial architect, the Stichler Group of San Diego, is
no longer working on the project.
"I prefer not to say why the project was stopped nor
why the Stichler Group is no longer on the project,"
said Ted Beshwate, the project manager for owner Trinity Health,
the fourth- largest Catholic health-care system in the United
States.
Los Angeles-based RBB Architects replaced Stichler on the
project in July 2003. The original construction manager, ProWest
PCM Inc. of Temecula, was dismissed in September 2001 as construction
manager of a $65 million, 232,000-sq.-ft. expansion of the
heart and vascular department.
"It's been quite a challenge, but a great learning experience,"
said Seals, who has worked for the general contractor since
he graduated with a degree in political science in 1999.
Matt's father, Steve Seals, and Steve Biehle, both of who
previously worked for Fresno-based Palmo Construction, established
Seals/Biehle in 1993. Seals/Biehle was the general contractor
for the expansion's first phasea 900-space, $8 million
parking structure and the structural steel and concrete portion
of a $10 million cogeneration plant. The firm replaced ProWest
as construction manager for the heart and vascular department
project in October 2001.
Located about 15 mi. north of downtown Fresno, St. Agnes
Medical Center was originally built on Herndon Avenue in 1975
as a 75-bed facility.
When Seals/Biehle became the construction manager for the
heart and vascular department last year, Seals inherited a
project that had 600 instruction bulletins (changes to the
original contract), was 12 months behind schedule and needed
a new set of drawings.
"RBB Architects has done a great job of updating the
contract documents and communicating on a regular basis with
OSHPOD," Seals said. "The project manager, Kevin
Boots, visits the site twice a week. RBB has the kind of health-care
experience that is necessary on a large, complex project like
this one."
 |
| PHOTO COURTESY OF SEALS/BIEHLE GENERAL
CONTRACTORS. |
Seals said his biggest concern since taking over as construction
manager has been keeping the trades on track for the expansion
of the heart and vascular department.
"We reigned it in and kept all of the prime trades focused
on the schedule despite all of the previous change orders,"
he added. "That's not an easy thing to do when you're
dealing with about 45 trades on a multi-prime project."
Phase two will be completed in early December. It also includes
a 50,000-sq.-ft. expansion for the catherization laboratory
department, which has been completed by Seals/Biehle, serving
as general contractor.
"It's been difficult getting [the heart and vascular
project] back on track," said engineer Dennis Enns of
Fresno-based New England Sheet Metal, the mechanical engineer
of record for the project. New England Sheet Metal has worked
for St. Agnes for 15 years. "Matt gets hit from all sides,
but he is doing well keeping track of everything," Enns
added. "We've all had to play a lot of catch-up."
The project's third phase includes a seismic retrofit of
the existing medical center and infill tenant improvement
on 40,000-sq-ft. of space. The $12 million phase has not been
scheduled.
Seals said a major contributor toward the progress made on
the heart and vascular department has been the work of Turlock-based
Partition Specialties, which has a $4 million contract for
dry wall, lath and plaster and metal stud and exterior framing.
"They've done a great job helping with the modifications
on contract documents and keeping the owner's standards,"
Seals said.
Terry McSweeney, project manager for Partition Specialities,
was equally impressed with the performance of Seals, who will
wed college sweetheart and current Seals/Biehle employee Gina
Machado on May 15.
"Matt works very well under pressure," McSweeney
said. "He's done remarkably well."
|