|
Major Upgrade for Manteca
Wastewater Treatment Plant to Be
Completed in July
The 20 million-gallons-a-day facility in the Central Valley
is expected to be up and running this summer, six to nine
months ahead of the original schedule. Upgrades will include
a higher level of treatment, nitrification process and new
pump station.
By Jennifer Bonnett
A $48 million upgrade to the Manteca wastewater quality-control
facility now scheduled for completion in July will produce
a higher level of treatment, nitrification process, ultra-violet
disinfection system and new filtration systems. A new pump
station will also be built at the site, located about 50 mi.
south of Sacramento.
"We've nitrified, added tertiary filters and have changed
our disinfection from chlorine to UV," said Phil Govea,
an engineer with the city. "We're calling this a state-of-the-art
facility."
Cities up and down California are facing state-imposed mandates
by the Regional Water Quality Control Board to make all wastewater
discharged into waterways fishable, swimable and potable.
The project in Manteca will be one of the state's most expensive,
Govea said.
The Folsom office of HDR is the construction manager. The
Concord office of Kiewit Pacific Co. is the general contractor
and the Manteca office of Nolte Associates is the engineer/architect.
The project's design work started in 1993 because of Manteca's
booming population, Govea said.
"Since (1993) it's gone through changes based on the
needs of Manteca, plus regulatory mandates have changed the
design," Govea added.
The existing treatment plant, which can handle 5 million
to 7 million gallons per day, will be able to take in up to
20 million gallons.
In November 2003, Anderson Pacific Engineering and Construction
of Santa Clara completed schedule A of phase three in the
four-phase project. Kiewit is handling schedule, B of phase
three, the largest part of the project. The project is separated
into four phases, with corresponding schedules (A,B,C,D) adjusted
for costs and constructability.
Kiewit's contract is for about $30 million. It includes all
the excavation, earthwork, concrete and mechanical work, according
to project manager Charlie Gardner. When it's finished. the
company will have done 80 percent of the work.
Although it was supposed to be a 26-month job, Gardner said
it is now scheduled for completion in July.
"We're months ahead of schedule because of the planning
and oversight of all the stakeholders involved," said
Warren Shannon, wastewater systems superintendent of Manteca's
public works department. "We give HDR a tremendous amount
of credit for that."
Gardner added, "Since we do a lot of emphasis on value
engineering, it looks like we'll be done some six- to nine-months
early."
Gardner said there are 80 to 100 employees on the site daily,
and their expertise and the partnership with the city have
made their job successful.
"We've been here over a year as construction manager
and everybody's contributed with bringing in new, good ideas
on how to finish faster and make the plant better," said
Jeffrey Inferrera, HDR's Folsom-based construction manager.
To help pay for the comprehensive project, ratepayers' sewer
bills may rise substantially to pay for a new city permit
needed for the plant upgrade. The proposed rate hike is under
appeal, Shannon said.
|