|
CalPERS' $153 Million Complex to Be Completed
This Summer
By Thomas York
CalPERS's new 560,000-sq.-ft. headquarters building-the largest
project downtown-remains on schedule for a summer completion.
CalPERs is a Sacramento-based agency that manages pension
funds for state and municipal employees.
The $153-million structure, bordered by Third, Fifth, Q and
R streets, features two steel-framed U-shaped buildings four
and six-stories high surrounding a courtyard.
|
|
|
The new CalPERS building in downtown
Sacramento, top photo, required a special foundation
because it lies atop an underground branch of the Sacramento
River. Turner Construction Co. is the construction manager
and Hensel Phelps Construction Co. is the general contractor.
S.J. Amoroso Construction was the contractor for the
foundation contract. Rendering courtesy of Kendall/Heaton
Associates.
Photo courtesy of CalPERS.
|
"The project is much more complicated than an office
building of comparable size," said Diane Procter, project
manager for CalPERS. "Working with multiple prime contracts
and getting it done quickly creates a lot of complexity in
terms of how the project fits together."
The Sacramento office of Turner Construction Co. is the construction
manager, Greeley, Colo.- based Hensel Phelps Construction
Co. is the general contractor and the architect of record
is Houston-based Kendall/Heaton Associates.
Hensel Phelps is now managing the last of the project's seven
bid packages.
Procter said the building required a special foundation and
equipment because it lies atop an underground branch of the
Sacramento River.
To install the foundation, Redwood City-based S.J. Amoroso
Construction Co. installed 1,900 auger cast piles, which contain
340,000 lbs. of reinforcing steel and 6,000 cu. yds. of concrete.
Procter said the contractor cast the piles in place to avoid
the noise and vibration associated with driving tradition
steel-rebar enforced concrete piles.
Before the foundation work began in late 2002, Marysville-based
Nordic Industries covered the two-square-block site with a
cement bentonite cut-off wall to shield against water leaks.
Nordic used a rare 118-ft.-tall auger, imported from Japan,
to excavate the garage 30 ft. below grade, then removed 230,000
cubic yards of soil before covering the floor with 24 in.
of concrete to protect against water intrusion.
Other subcontractors on the project include Benson Industries
Inc., which built the exterior wall; San Diego-based Helix
Electric; Pleasanton-based Herrick Corp., which erected the
steel frame; and Hayward-based Marelich Mechanical Co. which
installed mechanical and plumbing systems.
|