|
Breaking a Brutal Bottleneck: Rigorous
Roseville Interchange Project Reaching End of the Road
A $35 million improvement to the Douglas/Sunrise interchange
on Interstate 80 in the rapidly growing region northeast
of Sacramento is expected to expedite the daily flow of
94,000 vehicles. In addition to a flyover bridge, the project
includes an 800-ft. traffic tunnel.
By Robert Carlsen
The section of Interstate 80 that runs through the Roseville
city limits is called the "Roseville Bottleneck,"
and nowhere is it more congested than at the intersection
of Douglas Boulevard and Sunrise Avenue.
|
|
|
PHOTO COURTESY
OF CALTRANS
|
But that's being fixed. The city of Roseville and Caltrans
launched the Douglas/Interstate 80 interchange project in
February 2004 with the intent to divert about 15,000 vehicles
per day from the intersection to an 800-ft. tunnel and elevated
bridge.
Completion is scheduled for late September.
More than 94,000 vehicles a day go through the Douglas/Sunrise
intersection, clogging I-80 exits and entrances to the extreme.
"There's simply too much traffic cramming into too small
of a space," said Rhon Herndon, Roseville's senior civil
engineer.
Herndon said the city started working on the bottleneck in
1989, when it produced a capital improvement plan. Years of
study and planning resulted in a phase one project in 1998
that widened by one lane each the left turn and through lanes.
"That helped for a while, but we knew we had to do something
major eventually," Herndon said.
The phase two, $35 million project adds a new flyover bridge
to connect eastbound Douglas to southbound Sunrise and a tunnel
on-ramp from northbound Sunrise to eastbound I-80. It extends
the third outside westbound through-lane on Douglas over the
bridge to connect to the eastbound I-80 loop on-ramp and,
converts that single-lane loop on-ramp to a two-lane loop
on-ramp.
The project also moves the westbound off-ramp signal to the
east, realigns Oakridge Drive to maintain a signalized access
to Sunrise and adds an auxiliary lane on eastbound I-80 from
Douglas to Eureka Road.
Alamo-based R&L Brosamer Inc. is the general contractor
on the project. Howard Michael, a key project engineer with
Sacramento-based Stantec/URS, is the designer.
Deane Allin, R&L Brosamer's vice president and estimator,
said it was difficult to minimize impacts to the always-heavy
traffic and to get the tunnel and bridge completed before
the winter rains, but workers were successful.
"We also provided the temporary support systems required
to excavate under the Douglas bridge approach embankment-all
the while with traffic moving overhead," Allin said.
|
|
|
Two views of a
tunnel on-ramp from northbound Sunrise to eastbound
Interstate 80. The tunnel and flyover bridge were designed
to unclog the intersection of two at-grade streets,
Sunrise Avenue and Douglas Boulevard (aerial photo,
left, courtesy of Caltrans; photo, right, courtesy of
city of Roseville).
|
Herndon agreed that the tunnel and bridge were key elements
of the project, mainly because they were designed to "take
cars away from the intersection of Sunrise and Douglas."
Hossein Naghibzadeh, the city's project engineer, said that
the heavy winter rains delayed the project "minimally."
By the time the first day of spring arrived, crews had poured
70 percent of the concrete for the tunnel, he said.
More than 60,000 cu. yds. of dirt was dug out of the ground
to build the tunnel.
City officials estimate that 7,000 vehicles per day will
use the tunnel, reducing the number of northbound left-turning
vehicles at Sunrise and Douglas by 75 percent. The city recently
held a public "Name That Tunnel" contest, and the
winner will be announced this month by the Roseville Transportation
Commission.
Funding for the current project came from developer-paid
traffic impact-fees ($24.31 million) and the State Transportation
Improvement Program ($10.69 million).
|