|
Pasadena City Hall Overhaul Is a 'Thinking
Man's Project'
The $80 million seismic retrofit and restoration of the
78-year-old Pasadena City Hall will include installation
of friction-pendulum, double-concave base isolators, each
weighing 2.5 tons. The 240 base isolators will support the
entire weight of the 45,000-ton building.
By Greg Aragon
|
|
|
The 190,000-sq.-ft.
Pasadena City Hall is located on Garfield Avenue, two
blocks south of the 210 Freeway. The "California
Mediterranean-styled" building was completed on
Dec. 27, 1927, at a cost of $1.3 million (photo by Greg
Aragon).
|
After nearly 80 years of public service, Pasadena City Hall
is finally getting some support-structurally speaking, that
is.
"This is one of those projects that people want to be
a part of because it's seismic [and] the building is old,"
said Jim McLamb, vice president of operations for Clark Construction
of California, about the $80 million effort to seismically
upgrade and rehabilitate the city's majestic icon.
"It's a thinking man's project," McLamb added.
"You don't go in there like a bull in a china shop. You
walk in and strategize for a month and then you start it."
The 190,000-sq.-ft. Pasadena City Hall is located on Garfield
Avenue, two blocks south of the 210 Freeway. The "California
Mediterranean-styled" building was completed on Dec.
27, 1927, at a cost of $1.3 million.
Building a new foundation
Clark Construction, the current project's general contractor,
broke ground in March, when its crews began digging to a depth
of 9 ft. to demolish the structure's basement slab. Once this
hefty phase is complete, crews will build a new 100,000-sq.-ft.
slab and foundation that will sport 240 base isolators, which
will protect the building from significant damage during a
large earthquake.
"It's hard to give a magnitude scale but this [base
isolation] scheme is for a 500-year earthquake," said
Steve Marusich, senior engineer with San Francisco-based Forell
Elsesser, the company serving as the project's structural
engineer.
"The [retrofitted] building was designed to move a maximum
of 30 in. for the maximum credible earthquake, which is likely
to occur at the site, based on its distance from known faults
and the capacity of those faults to generate large earthquakes."
After the 1991 Sierra Madre earthquake, Dames & Moore,
a Los Angeles-based engineering firm, released a report that
found structural and non-structural damage to city hall's
dome and various parts of the building.
Then in 1995, after the 1994 Northridge earthquake, findings
by Forell Elsesser found: "The performance of Pasadena
City Hall in a major earthquake is expected to be poor; the
estimated large, inelastic displacements are typically well
beyond the capacity of the existing structure and may result
in serious life safety hazards and the potential for localized
structural instability."
"When we're done, the building will stay put if there
is an earthquake and the ground will move around the building,"
said Clark project executive Dennis Breen, who is working
on his first base-isolation project.
The base isolator used on this project is called "friction-pendulum,
double-concave," which means that in the event of a major
earthquake, the building will move like the pendulum of a
grandfather clock, up the slick sides of the concave isolators
and then back to its original position.
Designed and built by Vallejo-based Earthquake Protection
Systems Inc., each isolator measures 3.5 sq. ft. and weighs
about 2.5 tons. When all of the isolators are installed, they
will support the entire weight of the 45,000-ton building.
Preserving the historic integrity
Marusich said that base isolators were used on this project
primarily because the building is "historic and very
massive," which lends itself to base isolation.
"If we tried conventional retrofit schemes, which entail
putting in concrete shear walls and things of that nature,
[which] are very intrusive, we would end up losing a lot of
historic features to accommodate the structural strengthening,"
Marusich added. "And the city wanted to keep [city hall]
as pristine as possible. [Base isolation] is one of the few
options that's available to achieve that goal."
He said that with this method, at least 75 percent of the
structural work is hidden in the basement level and in the
foundations.
Listed on the National Register of Historic Places, Pasadena
City Hall is constructed of reinforced concrete with stucco
rendering, elaborate cast stone ornamentation and tile roofs.
The building was designed by the San Francisco architectural
firm of Bakewell and Brown, which turned to the Renaissance
style of 16th Century Italian architect Andrea Palladio for
inspiration.
Architectural Resources Group of San Francisco is the project
architect for the current seismic upgrade and restoration.
Featuring 235 rooms, the rectangular-shaped, three-story
city hall stretches 351 ft. between its north and south sides
to 242 ft. between its east and west edges. On the east side
is a one-story arcade, and on the other three sides are small
towers at each corner and a signature, six-story dome towering
206 ft. above the main west entrance.
|
|
|
A friction-pendulum, double-concave
base isolators like this one will be installed below
Pasadena City Hall (photo courtesy of Forell Elsesser).
|
The building wraps around a Spanish Colonial-themed courtyard,
which features a 22.5-ft.-tall cast stone Baroque fountain;
paths of crushed granite-lined flower beds; cloistered arches
paved with red Padre tile; and numerous California live oak
trees.
Clark's crews recently demolished the arcade and courtyard
after removing the fountain (which will be put back when construction
is finished) to insert base isolators underneath, and have
dug a 6-ft.-wide "moat" around the entire perimeter
of the project to allow for horizontal movement in a quake.
Crews also have removed the large steps to the main entrance
in order to install steel slider plates beneath them and have
covered the original sidewalk in front of the building to
protect it during construction.
On the exterior, crews will refurbish all cast stone elements,
plaster and copper cladding on the dome. And on the inside
of the building, they will restore an original elevator cab,
as well as replace all mechanical, electrical and plumbing
systems.
The retrofit project was approved by City Council in 2003.
It is being paid for through a combination of Federal Emergency
Management Agency funding, state grants; local tax revenues;
bond sales, private contributions and an increase in the percentage
of electricity revenues that are transferred from the city's
light and power fund to the general fund annually.
The project is currently about 15-percent complete, with
basement demolition finished and excavation in progress. The
entire project is scheduled for completion in summer 2007.
Until then, all City Hall offices will remain in temporary
bungalows across the street.
Double Off-Grid Method Is Faster>>
|