|
All Together Now
Simultaneous Construction of Pipeline
Wasn't Planned
Permits were approved nearly at the same time for Sacramento
County Regional Sanitation District's $800-million capacity
improvement program, causing construction to start concurrently
on all three pipeline segments. When the project is completed
next fall, 50 mi. of new pipes will carry wastewater under
the Sacramento River to a regional treatment plant.
By J.T. Long
When the rush of tunneling ends next year, more than 50 mi.
of new sewer pipeline will carry wastewater from the fast-growing
Natomas and West Sacramento areas under the Sacramento River
to the Sacramento Regional Wastewater Treatment Plant.
|
|
|
Neal Allen, principal
engineer with the sanitation district, said the most
challenging aspect of the entire project is the boring
of two 2,000-ft. long, 15-ft.-diameter tunnels 40 to
60 ft. under the silt and gravel floor of the Sacramento
River (photo courtesy of the Sacramento County Regional
Sanitation District).
|
The Sacramento Regional County Sanitation District, which
has identified 120 mi. of pipeline capacity improvements for
the next 20 years, didn't plan to construct all $800-million
worth of interceptor lines at once, but a delay in permitting
meant that instead of staggering major projects, three big
ones- the Bradshaw, Arden and Lower Northwest Interceptor-are
all boring, pouring and pumping at once.
"Everything broke [the permitting process] at once,"
said Neal Allen, principal engineer with the sanitation district.
LNWI Is Divided Into 9 Contracts
More than half the work, $600 million, is contained in the
Lower Northwest Interceptor, a 19-mi. pipeline being built
with the aid of more than 22 contractors and subcontractors
using state-of-the-art digging equipment.
To assure competition and contracting capacity, SRCSD divided
the LNWI into nine contracts. They include two new pump stations,
five pipeline projects and 14 tunneled crossings, two of which
will be under the Sacramento River. During peak wet weather,
the system will handle as much as 200 million gallons per
day.
Despite one of the wettest winters and springs in recent
memory, "the projects are proceeding on schedule,"
said John Buttz, LNWI program manager and vice president of
MWH of Broomfield, Colo.
A Vital Link
The LNWI alone required the acquisition of right-of-way for
more than 230 parcels, 122 permits and satisfying a stakeholder
list of more than 5,000 people. It will link some 200,000
homes, many in the fast-growing Natomas and West Sacramento
areas, to the Sacramento Regional Wastewater Treatment Plant
in Elk Grove, which was last expanded in 1982.
Major components of the LNWI include a pair of $115-million
pump stations designed by Omaha, Neb.-based HDR Inc. The stations
will ultimately include six 2,000-hp pumps with self-cleaning
elements and odor control systems. Full standby power will
be provided for both stations from six 2000-KW diesel generators.
Allen said the most challenging aspect of the entire project
is the boring of two 2,000-ft. long, 15-ft.-diameter tunnels
40 to 60 ft. under the silt and gravel floor of the Sacramento
River, a $44-million contract. The decision to go with one
big tunnel using a manned Lovat Tunnel Boring Machine (TBM)
was not an easy one. SRCSD considered horizontal direction
drilling and paired microtunnels (methods used on other segments
of the overall project), including the $14-million Arden Parallel
Force Main, where 10,400 ft. of 60-in.-diameter parallel tunnels
are being dug under the American River's soft clay soil using
unmanned TBMs.
Dave Young, senior design manager for consultant Hatch Mott
McDonald, a Millburn, N.J.-based consulting engineering firm
that was awarded the $44-million design contract for the northern
and southern Sacramento River crossings, said, "We had
to convince the district that the large diameter pressurized
tunnel using a tunnel boring machine was hands-down the best
alternative for the Sacramento River crossings. It was equal
in cost, but superior in schedule and operations and maintenance."
They Look Like Space Capsules
The method chosen called for two 30-ft. diameter Lovat TBM
machines that look something like space capsules fitted with
a cutting wheel at the front that turns the rock and gravel
into a slurry in a pressurized chamber and then dumps the
sludge out the back into spoil carts that are wheeled to the
surface at a six-degree angle like a train. As the TBM moves
forward, it lines the tunnel with a pre-cast concrete lining.
Upon completion of the tunnels, twin-welded steel pipes are
installed and the void is filled with low-density cellular
concrete, a lightweight foam and cement slurry that includes
suspended air bubbles.
The decision to use this method was based largely on the
type of soil. The Sacramento River contains gold mining tailings,
a condition that Ray Costa, senior project manager for San
Diego-based Engineering firm Kleinfelder Inc., which performed
engineering work for parts of the project, described as "digging
through marbles the size of basketballs." The larger
shaft size and increased horsepower of the Lovat TBM can deal
with these materials without getting stuck.
The area also has a high water table. In order to dig the
launch and receiving pits for the TBM, excavation subcontractor
Blue Iron Inc. of Woodbridge had to de-water by pumping groundwater
out of wells. The discharge then had to be treated and sent
through temporary pipelines to two sites predetermined by
the Central Valley Regional Water Quality Control Board.
Another factor was space. The large TBM could not be used
on the Arden project because space constraints from levees
and urban development didn't leave room for the angled approach
tunnels required by SRCSD for maintenance reasons.
In contrast, the Bradshaw Interceptor, which runs through
the heart of the urbanized area, used a combination of microtunnels
and open cut methods. The 36- to 120-in.-diameter reinforced
concrete pipes are buried 30-ft. deep. The path crosses three
high voltage easements, five creek channels and one railroad.
Work was divided into five sections to space out impacts to
residents.
"Schedule risk was the deciding factor," said Neil
Mann, construction team lead for the project and an MWH employee.
"We can't delay this project because this capacity is
needed now for all the development going in."
Because of flood concerns near the levee, teams can only
work during the spring and summer, a requirement that will
stretch the entire project out over two years with completion
expected in fall 2006, just in time to serve all the residential
plumbing now under construction in the region.
|