|
Initial Pipeline Phase Finishes Early
Steel Shoring Box Shaves Several
Months From Schedule
A 3-mi. segment of a 13-mi.-long pipeline system underway
for the Orange County Water District was completed nearly
one year early due to a variety of factors. The work is part
of a $486.9 million upgrade to the district's ground-replenishment
system. The pipeline will carry 72 million gallons of water
a day from a purification plant in Fountain Valley to settling
basins in Anaheim.
By Kathy Lee Scott
An ingenious safety device, the elimination of pre-excavation
soil stabilization, and the ability to work during the rainy
season, allowed general contractor Ken Thompson Inc. of Torrance
to finish a 3-mi. portion of a 13-mi. water pipeline for the
Orange County Water District in June, almost one year early.
"We employed a unique method of shoring up the trench
that reduced cave-ins," said Dan Deming, executive vice
president of Ken Thompson. "We used a giant, horizontal
system, essentially a safety box, into which the pipe and
crew fit."
|
|
|
Crews for Ken Thompson Construction
work underneath Interstate 405 at Euclid Avenue in Fountain
Valley (photo by Kathy Lee Scott).
|
The all-steel, 61,000-lb. box was specially constructed for
the job by Mike's Welding of Fontana.
"The shoring shields are 10 ft. high and 54-ft. long,
and they open at the top and bottom with 7-ft. spreader bars
across the top," said Mike Bokulic Jr., vice president
of Mike's Welding.
An excavator pulls the shields with the crew inside.
The pipeline is part of a $486.9-million ground-replenishment
project approved by the water district in 2001. It includes
a new, $292-million water purification plant and new $13-million
barrier wells that will hold back seawater from contaminating
the underground aquifer. The plant will produce initially
70,000 acre ft. of potable water per year, with a potential
annual production of 100,000 acre ft.
J.F. Shea Construction Inc. of Walnut is the general contractor
and expects to finish in August 2007. The barrier wells should
be finished by June 2006.
The 3-mi. pipeline section is only one of two sections that
Ken Thompson is constructing for the OCWD. The general contractor
won two bids worth almost $43.7 million on the pipeline project,
and Corona-based Colich Construction Inc. won the third, a
4-mi. segment that is worth $16.9 million. Thompson's second
segment is 6-mi. long.
Pipeline Runs From Fountain Valley to
Anaheim
The 13-mi. water pipeline begins in Fountain Valley, then
follows the Santa Ana River flood control channel north to
two settling basins in Anaheim. Along its length, the pipeline
trenches range in depth from 11 ft. to 30 ft., said Shivaji
Deshmukh, assistant director of engineering for OCWD.
It tunnels under the five major freeways in Orange County
and sits within the western levee of the flood control channel
for 12 of its 13 mi. Just south of State Route 91, the pipeline
branches north from the Santa Ana River to the OCWD-owned
Carbon Canyon Diversion Channel before ending at the Miller
and Kraemer settling basins on Miraloma Avenue. There, it
dumps its water load that then percolates through the soil
into the groundwater.
At its start, the pipeline's diameter is 78 in. It then decreases
incrementally to its final diameter of 60 in. at its end.
The pipeline will carry 72 million gallons a day, or 70,000
acre-ft., to the retarding basins. One acre ft., or 326,000
gallons, will cover a football field to 1 ft.; that quantity
provides enough water to two families for a year.
The water source is secondary treated sewage water from one
of Orange County Sanitation District's two treatment plants
in Fountain Valley; the fluid will be sent through the purification
plant, then the pristine water will be pumped north to Kraemer
and Miller basins to trickle down to the groundwater.
"It will give us water when we need it and not when
the Metropolitan Water District has surplus to sell,"
said OCWD spokesperson Ron Wildermuth.
Of its 500,000-acre-ft. annual supply, the water district
buys about 25 percent from Los Angeles-based Metropolitan
Water District of Southern California throughout the year,
and withdraws 75 percent from its underground aquifers. Once
the project is complete, the district will have a reliable
source of drinking water for its 2.3 million customers, Wildermuth
said.
Early Completion Saves District $350,000
|
|
|
Welder from Colich
Construction works on a 4-mi. segment of 66-in. pipeline
alongside Chapman Avenue west of State Route 57 and
within the west levee of the Santa Ana River (photo
by Kathy Lee Scott).
|
Construction on the northern 3-mi. portion of the water pipeline
began in October 2003. "We didn't get any bonus for finishing
early," Thompson's Deming said.
However, the water district saved about $350,000 from its
budgeted $17.8 million for this portion of the pipeline project
because of the early completion.
"We eliminated the requirement of stabilizing the soil
before boring," said Deshmukh, based on the contractor's
recommendation.
Another factor in the early finish was an agreement struck
by OCWD and the U.S. Army Corps of Engineers, which regulates
activity around the flood control channel. "They allowed
us to work in winter as long as the water flows in the river
were under 5,000 csf (cubic feet per second)," said Mike
Markus, project manager for OCWD.
"We'd wait for the rain to stop, then went to work,"
Deming said. "The rain just drained from the sandy ground,"
he added.
Tunneling displaced lots of sandy, river-bottom soil, which
the contractor sold to ready-mix companies. With permission,
it also spread some soil in nearby ponds and depressions,
Deming said.
The majority of the work was done before the winter rains
came, and because the water district owned part of the land
on which the northern section of the pipeline is situated,
it could control the work schedule, Deshmukh said.
"The biggest factor (for early completion) was the district's
cooperation," Deming said. It didn't want anything to
hold up construction of the section that runs from Katella
Avenue to Miraloma Avenue, he added.
Ameron Makes Pipes
Fifty-two thousand lin. ft. of 3/8-in.-thick steel pipes,
coated with cement mortar both inside and out, were manufactured
by Ameron International of Rancho Cucamonga for Ken Thompson.
Because such a configuration is not rigid, in engineering
terms, they arrived with wooden bracing inside, Markus said.
Once the pipe sections are welded together, hand-patched inside
and out with mortar and the trench backfilled, they are stable,
he added.
"Such pipes are normal for water systems," Markus
said.
Colich Construction started production on the pipeline's
middle section in mid-2004 and is aiming for a February completion,
said Jeremy Juarez, Colich's project manager. "We still
have a lot of tunnels to dig," he added.
In the center section, the water pipeline runs from 17th
Street north to Katella Avenue in Anaheim and uses about 17,000
lin. ft. of pipes. "We've got some tight spots to lay
pipe," Juarez said. The 66-in.-diameter pipes were manufactured
by Northwest Pipe Co. of Adelanto.
In the tunnel under Interstate 5, Colich's construction crews
encountered debris, mainly old fence posts and chain-link
fencing, about 30-ft. down, Deshmukh said. "They had
to change their boring machine from a closed face to one with
an excavator," the OCWD engineer added.
Markus said he thought the debris came from a 1938 attempt
to restore the river bank after a flood.
Ken Thompson crews began work on the 6-mi. southern pipeline
section in September 2004, with a finish date set for August
2006, Markus said.
"If it goes as planned, we'll complete this a year early,
too," Deming said.
As with the finished section, Ameron International manufactured
the pipes, whose diameters range from 78 in. to 66 in. for
this southern section. It originates at the new water purification
plant, then runs from Ellis Avenue in Fountain Valley to 17th
Street in Santa Ana.
Along the entire pipeline, six 5-in., empty PCV conduits
were installed, Markus said. "They can be rented for
fiber optics in the future," he added.
Three butterfly valves that cover the pipe's diameter were
inserted at spots along the 13-mi. length so maintenance workers
can isolate portions for future repairs, Deshmukh said. The
valves also prevent backflow once the water is pumped from
the treatment plant, he added.
|