|
Qualcomm Construction Continues
Roel Construction is overseeing
17 construction projects totaling about 2.4 million sq. ft.
for the San Diego-based digital communications giant. The
two largest projects- an $80-million office building and a
$130-million complex on a 10-acre site-will be finished by
the end of the year.
By Greg Aragon
It's hard to drive through the Sorrento Mesa area of northern
San Diego these days and not notice a Roel Construction Co.
or Qualcomm sign on the side of the road.
|
|
|
Spanning 415,000
sq. ft., Qualcomm's Building WT is a 12-story, $80-million
tower being built for its chip technology department.
It will accommodate 1,350 employees. Inside the tower
will be a cafeteria, fitness area, offices and laboratory
space. There will be basketball and volleyball courts
outside (photo by Greg Aragon).
|
The San Diego-based companies are currently working together
on 17 construction projects, totaling roughly 2.4 million
sq. ft. and nearly $350 million.
Qualcomm Inc., a global, digital wireless communications
giant, is the developer/owner of the projects, and Roel is
serving as the general contractor.
"We have a very healthy problem," said Chuck Nichols,
senior director of construction for Qualcomm. "It's called
growth, and we need [to build] these projects to support the
worldwide demand for Qualcomm's technologies and applications."
Located about 12 mi. north of downtown San Diego, near Interstate
805, Sorrento Mesa is an area filled with companies involved
in telecommunications and wireless technology.
Qualcomm's two largest projects are called Building WT, which
will be completed in October and was about 70-percent complete
in January, and Building N, which will be finished by the
end of the year.
Spanning 415,000 sq. ft., Building WT is a 12-story, $80-million
tower being built for Qualcomm's chip technology department.
It will accommodate 1,350 employees.
Inside the tower will be a cafeteria, fitness area, offices
and laboratory space. There will be basketball and volleyball
courts outside.
Also on the 10-acre site-known as the W Campus, Roel is remodeling
an existing 160,000-sq.-ft. building; constructing a seven-story,
1,300-space parking garage; and erecting a 24,000-sq.-ft.
central plant. These structures bring the total construction
cost for this project to about $130 million.
David Bates, Roel project manager, said working on all these
separate projects at once and on one site has not been easy.
"With multiple projects all progressing on the small
site, the coordination between the jobs is very important,"
Bates added. "There is not only the physical tie between
the building for power and other utilities, there is also
the coordination of the construction activities.
"For instance, there is only 60 to 70 ft. between the
office tower and the parking structure. When concrete is being
poured for the parking structure and the pump and concrete
trucks are using the access road between the two buildings,
no other trades can use the road."
|
"We have a very healthy problem. It's called growth,
and we need [to build] these projects to support the
worldwide demand for Qualcomm's technologies and applications."
-Chuck Nichols, senior director
of construction for Qualcomm.
|
Bates said that "very close coordination with the subcontractors,"
which included bi-weekly meetings, has been key to overcoming
the hurdles.
Construction on WT began in March 2004. San Diego-based Delawie
Wilkes Rodrigues Barker is the architect.
Down the street from WT, on Morehouse Drive, is the $103-million
Building N project, which will serve as the new corporate
headquarters for Qualcomm. Also designed by Delawie Wilkes
Rodrigues Barker, the 475,000-sq.-ft., 10-story building will
feature a 550-seat auditorium, eight-story atrium and office
and lab space.
Brent Hughes, Roel's senior project manager, said the building's
fancy exterior stands out.
"The skin [features] a unique system and components;
it consists of limestone, metal panels and glass," Hughes
said. The limestone came from Italy, the metals from Thailand
and the unitized curtain wall from Pomona.
|
|
|
The $103-million
Building N project will serve as the new corporate headquarters
for Qualcomm. The 475,000-sq.-ft., 10-story structure
will feature a 550-seat auditorium, eight-story atrium
and office and lab space (photo by Greg Aragon).
|
"It was a global effort," Hughes added.
The project manager said he liked the idea of the curtain
wall arriving at the project ready to go.
"The unit comes out with the glass and stone already
in it; everything is already assembled. You just hang the
unit off the building and you're done," he added.
It took about 4,500 pieces-ranging anywhere from 2-ft. wide
and 15-ft. tall to 8-ft. wide and 20-ft. tall-to cover the
building.
The project, which broke ground in August 2004, is currently
about 60-percent complete. Exterior glazing was under way
in early January.
Other project highlights include two parking structures:
Garage A is a five-story (two stories below ground and three
above), 800-space, 290,000-sq.-ft. structure. Garage B is
565,000 sq. ft. in seven stories (two below ground, five above)
and can park 1,650 cars.
Roel and Qualcomm officials declined to disclose the cost
of the parking structures.
The job also features a 50- by 50-ft. helipad on the roof.
"We're a global company and require global travel, and
this pad will facilitate travel to our corporate jets,"
Nichols said.
|