|
Greener Than Green
New Kaiser Modesto Project Utilizes
New Sustainability Methods, Products
By Greg Aragon
With each new hospital campus construction project, Kaiser
Permanente ups the ante for sustainability. And nowhere are
the green elements as striking as its current $462 million
project in Modesto.
Though
Kaiser will not be seeking a third-party certification under
any green building rating system, the firm is using the Kaiser
Modesto Medical Center project to test a variety of green
pilot programs.
One main green feature is the extensive use of pervious asphalt.
General contractor Harbison-Mahony-Higgins Builders, Inc.
of Sacramento used 4,400 tons of permeable pavement spread
atop all parking areas. This type of coating is more porous
than average pavement and prevents wasteful run-off during
heavy rains by giving water room to seep down through its
surface. In so doing it acts as a natural filter, removing
chemicals before the water reaches the ground.
To apply the surface, crews first excavate the site and install
a filter fabric, followed by a perforated pipe to distribute
the water evenly. They then they apply a two-inch washed rough
aggregate before laying down the pavement.
Mike Hrast, Kaiser project director, said that this project
represents the largest application of permeable pavement west
of the Mississippi and Kaiser estimates the process will save
approximately $290,000 in project costs.
Other green features include photovoltaic screens to shield
rooftop equipment and generate electricity; photovoltaic parking
lights along the entrance road; rubber flooring instead of
vinyl composition tile (VCT), which is known to leach toxins;
PVC-free carpeting that is 100 percent recyclable; and a low-maintenance
grass roof over the main lobby, which will reduce heating
costs and add an estimated 20 years to the life of the roof.
A pilot study also determined that the use of cotton batt
insulation resulted in better acoustic properties than traditional
fiberglass, plus the batt insulation is made from 100 percent
recycled cotton and other natural fibers.
Meanwhile, the Kaiser Modesto Medical Center project is moving
along towards a November 2007 completion. Its design may look
familiar, since it is using the same template design as the
other Kaiser projects in Vacaville, Antioch, and Irvine.
"The advantages to the template approach are that we
can reduce design fees on future hospitals, accelerate the
approval process for these hospitals, and I believe that contractors
will be able to bid these projects more competitively in the
future based upon their experience," said Hrast.
The facility sits on 50 acres in Modesto, 90 miles east of
San Francisco. It consists of a five-story, 400,000-sq.-ft.
main hospital with two nursing towers and 224-bed; a 254,000-sq.-ft.,
four-story support wing; and a 29,000-sq.-ft. central utility
plant. The project also features 25 acres of parking and 10
acres of landscaping.
Facilities include six operating rooms, 36 birthing rooms,
20 ICU beds and 24 Neonatal Intensive Care beds. All patient
rooms are single-bed units with a private restroom and a window
to allow in natural light. Each will offer internet access
and sleeper sofas for family members.
Because
the Modesto hospital is based on a template, architects were
able to concentrate on fine tuning instead of coming up with
a whole new design.
"The biggest benefit of a template is being able to
see what was done before and think of ways to improve it,"
said Michael Wilson, project director with San Francisco-based
Chong Partners Architecture, which designed the project in
a joint venture with San Francisco-based SmithGroup and Sacramento-based
Lionakis Beaumont Design Group. "Each time you go through
this process, you are refining the design and the construction
issues, so it's a new way of doing architecture."
Hrast said that improvements made this time around include
things like "logically" adjoining departments between
the hospital and the support wing to make it easier for patients
to arrive at proper hospital locations.
"For instance, a patient might have an appointment for
a surgical procedure and perhaps forget if it's in our outpatient
surgical suite or in the inpatient OR," said Hrast. "All
the [patient] has to do is arrive at the second floor where
we have one waiting area for both departments."
Other examples include moving the maternity ward next to
pediatrics and obstetrics-gynecology to keep these patients
and doctors in the same area, and breaking up the traditional
central nursing station and spreading it throughout the building
to better reach different patients.
The Project Team
Owner: Kaiser Permanente
General Contractor: Harbison-Mahony-Higgins
Builders Inc.
Architects: Lionakis Beaumont
Design Group, Chong Partners Architecture, SmithGroup
Civil Engineer: Mark Thomas
& Associates
Structural & Mechanical Engineers:
Lionakis Beaumont Design Group, ARUP, Capital Engineering
|