Cover Story - July 2009

Highway Top 25 Projects

By Robert Carlsen

This year’s list includes a massive I-15 managed lane project, two SR 52 extension projects, a new freeway to the Mexican border, a city of Elk Grove interchange bridge project and a road reconstruction in the Shasta-Trinity National Forest.

California’s highways and roadways are currently getting a shot in the arm with infrastructure stimulus funds from the American Recovery and Reinvestment Act, but a number of high-profile road projects also broke ground last year despite a freefalling economy and with little or no extra federal money.

Among them are the Interstate 15 south and north segment projects and another phase of the U.S. 101 widening project in Napa, Sonoma and Mendocino counties.

advertisement

Population growth in the Inland Empire and along San Diego County’s I-15 corridor has led to a major case of congestion, with commutes between State Routes 163 and 78, a 20-mi stretch, taking 30 to 45 minutes.

And with planners estimating that a daily peak of 290,000 vehicles will increase to 380,000 vehicles by 2020, increasing that drive to 90 minutes or more, Caltrans and the San Diego Association of Governments had no other choice but to expand.

That three-segment project, the I-15 Express Lanes, is well underway and the south segment, with a construction cost of $481 million, tops our list of the Top 25 Highway Projects for 2009.

I-15 is a major route from the Southwest into the Intermountain West, connecting San Diego and Los Angeles to Las Vegas, St. George, Provo, Salt Lake City, Pocatello, Idaho Falls, Butte and Great Falls. It runs 1,433 mi.

The U.S. 101 HOV/Widening project near Windsor was among our top 25 highway projects that began in California in 2008.
The U.S. 101 HOV/Widening project near Windsor was among our top 25 highway projects that began in California in 2008.

Since I-15’s completion in the 1970s, California, Nevada and Utah have consistently ranked in the fastest-growing areas of the U.S. and the I-15 corridor has grown in popularity with the population increases. It is now one of the most crowded freeways in the state.

To relieve the congestion in the San Diego segment, Caltrans is expanding I-15 with a four-lane, 20-mi express lane in the median.

Stretching from SR 163 north to SR 78, the new lanes are the first adaptable, high-tech transportation project configured to adapt to the needs of local travelers, commuters and commerce. The lanes will serve vanpools, carpools, buses, and FasTrak customers. Tolls for FasTrak users will vary from 50 cents to $8 depending on the distance traveled, the time of day and the level of traffic congestion on the Express Lanes.

The I-15 Express Lanes will feature a moveable barrier for maximum flexibility (similar to the moveable barriers on the San Diego-Coronado Bridge); multiple access points to the general purpose highway lanes; and direct access ramps for high-frequency Bus Rapid Transit service.

The middle segment has opened in two phases. The first phase from SR 56 to Rancho Bernardo Road opened in September. The second phase from Rancho Bernardo Road to Centre City Parkway opened in March. The north segment and the south segment are scheduled to open to traffic in 2011 and 2012, respectively. Each segment is made up of multiple construction units.

Caltrans and SANDAG are overseeing the I-15 South Segment project.
Caltrans and SANDAG are overseeing the I-15 South Segment project.

Several bridges along this stretch are being modified to accommodate the managed lanes. The Pomerado Bridge, which reopened for public use in January 2007, was demolished and completely rebuilt in nine months. The new and improved bridge features four lanes, a pedestrian and bicycle path, a signalized intersection at the west end, upgraded seismic standards and aesthetic improvements to coordinate with other construction in progress on I-15.

Caltrans I-15 corridor director Gustavo Dallarda says that in the five years he’s been involved in the project, coordination between multiple contractors is the key issue.

“We’re building a freeway within a freeway while trying to keep up to 300,000 vehicles moving,” Dallarda says. “There’s a lot of night work and closures and when you work with many contractors and up to 300 workers at any given time, you need good coordination.”

The south segment (units 1 and 3) is being managed by Longmont, Colo.-based Flatiron West; Coffman Specialties of San Diego is managing unit 2. Flatiron West also managed four units of the middle segment project.

Chris Wyss, Flatiron’s project manager-unit 3, south segment, says the job on this section, from the Sabre Springs/Penasquitos Transit Station to the Mira Mesa Transit Station, consists of the widening of the southbound lanes.

“All along the south segment, the neighborhoods are right up against us,” Wyss says. “We’ve had to alter our sequences due to noise regulations, especially during night work.”

Funding for the south segment comes from TransNet, the county’s half-cent sales tax for transportation improvements (12%), State Transportation Improvement Program (13%), Prop 1B (73%) and the Congestion Mitigation and Air Quality program (2%).

Meanwhile, Caltrans is working with Berkeley-based OC Jones and Sons on the U.S. 101 HOV/Widening project. This phase of a multiphase 101 widening program in the North Bay Area widens the highway from four to six lanes to expand about 7.6 mi of HOV lanes from Steele Lane in Santa Rosa to Windsor River Road in Windsor.

Work includes excavation, grading, paving, bridge widening, slab replacements and concrete barriers.

“There’s also a significant amount of electrical and traffic monitoring equipment installation,” says Randall Husch, OC Jones project manager.

Husch adds that the major challenge on this project is the schedule.

“Caltrans advertised this as an A and B project, meaning you bid dollars and working days,” Husch says. Due to the increased competition for infrastructure jobs these days, OC Jones obviously “bid an aggressive schedule,” but so far everything is going smoothly, he says.

Funding for the $120-million project comes from the State Highway Operation and Protection Program, Corridor Mobility Improvement Account, Fed-Demo and Sonoma County Measure M funds.

 