|
Green-Leaning Detention Center in San Leandro
The 390,000-sq.-ft. Alameda County
Juvenile Justice Center project seeks a LEED rating primarily
through such energy-saving elements as a "cool"
roof and water retention ponds.
By Robert Carlsen
Green building techniques and products, along with an unusual
community outreach program, are highlighting the construction
of the $140-million Alameda County Juvenile Justice Center
project in San Leandro.
|
|
|
The detention
center project in San Leandro consists of three building
areas: a 196,000-sq.-ft. housing building, 71,100-sq.-ft.
support building (with classrooms, counseling rooms
and administration offices) and 122,000-sq.-ft. courts
building. There will also be exercise yards and a gymnasium
(photo courtesy of Hensel Phelps Construction Co.).
|
The project is a design-build partnership of the San Jose
office of Hensel Phelps Construction Co. and HOK Architects
of San Francisco. The joint-venture construction management
firm is Vanir/Cornerstone of Sacramento and San Francisco.
Cornerstone Concilium Inc., a San Francisco-based construction
management and facilities consulting firm, has been contracted
by Alameda County to make sure the project meets certain outreach
goals and milestones, including a project intern program that
involves former juvenile detention members.
Scheduled for completion in about a year, the 390,000-sq.-ft.
facility is located on county-owned, unincorporated land adjacent
to the current juvenile hall facility, which first opened
in 1953, and by 1997 was "old, outdated and difficult
to maintain," Alameda County officials said.
After years of studies and need assessments, the county,
which also considered a site in nearby Dublin, found the San
Leandro site more cost effective in the long run.
The project consists of three building areas: a 196,000-sq.-ft.
residential building, 71,000-sq.-ft. support building (with
classrooms, counseling rooms and administration offices) and
122,000-sq.-ft. courts building. The facility will have the
capacity to house 360 minors; 90 will be classified as maximum
security and 270 classified as medium security. There also
will be exercise yards and a gymnasium.
Jim Reilly, senior construction manager for Vanir/Cornerstone,
said construction materials include structural pre-cast concrete
panels for the residential building and architectural pre-cast
concrete panels for the courts building. Other materials and
features include CMU masonry, structural steel, parapet roofs
and single-ply membranes.
The contract also calls for a four-pipe HVAC system, security
package, medical facility, nine elevators, boilers, three
parking lots, landscaping and site improvements.
Sean Carolan, project manager for Hensel Phelps, said site
improvements on the brownfield site involved moving 300,000
cu. yds. of dirt.
To get a leg up on some U.S. Green Building Council LEED
points regarding waste management issues, Carolan said that
during demolition of some onsite buildings (which were formerly
part of a boy's summer camp) the construction team ground
up the concrete foundations and used them for fill. In fact,
most of the sloped site had to be built up, he said.
Carolan said the main challenge was finding LEED points in
the design process because the county requires new public
buildings to qualify for at least a LEED-certified rating
by the U.S. Green Building Council.
"You have to consider this is a 24-hour detention center,
with certain security issues involved, which hampers some
traditional sustainable options," he added. "Our
main goal was to make the facility as energy efficient as
possible."
Alan Bright, HOK's project manager, and Steve Slosek, project
architect, said that energy savings from the design of the
facility exceeded Title 24 state energy efficiency standards
by 40 percent.
"One of the main energy elements is the use of a 'cool
roof,' -- a light-colored component that will cover more than
180,000 sq. ft. of the facility and deflect the sun's rays,"
Slosek said.
Bright said other sustainable elements include a 40-percent
reduction of water usage, with the installment of low-flow
toilets and waterless urinals, a 50-percent reduction of water
use for irrigation and the protection of surrounding wetlands
with the construction of retention/detention ponds and bio-swales
that reduce storm water runoff.
Carolan said key members of his construction team include
Beverly Prior Architecture of Oakland, which is designing
the exterior and other elements; KPA Group of Oakland, the
structural engineer; and Loisos + Ubbelohde, also of Oakland,
which is the energy consultant.
|