|
Lessons Learned
A Combination High and Middle School
Project in Elk Groves Reuses Design
By Robert Carlsen
Though housing starts have stalled recently, Elk Grove continues
to be one of the fastest growing cities in the country, and
the pace of school construction belies that growth.
A
two-school project - numbers 60 and 61 on the Elk Grove Unified
School District campus roster - is now underway in the southern
Laguna Ridge region, which is expected to house tens of thousands
of new residents in the coming years.
The district, currently the home to 60,000
students, has opened 23 schools in the past 10 years, plans
to build 19 new schools to meet a projected enrollment of
80,000 students by the year 2010.
With the cost of building schools continuing
to rise, driven by soaring land prices and construction expenses,
the school district is using a design tactic that is saving
it major dollars.
The $80 million, 209,000-sq.-ft. Cosumnes
Oaks High School/Elizabeth Pinkerton Middle School project
design is borrowing from original designs made four years
ago with the Franklin High School/Toby Johnson Middle School
project.
And the same team that last year completed
the Pleasant Grove High School/Katherine Albiani Middle School
project - general contractor Lathrop Construction of Benicia
and architect Stafford King Wiese of Sacramento - have worked
out just about all the kinks in this new project.
"The district is saving lots of money
by reusing the design," said Carmine Faro, construction
manager for Stafford King Wiese. "The classroom buildings
are pretty much the same, as is the configuration of the campuses.
Maybe some of the roofs are different.
"One of the major design challenges
is that the site has a collection of old oaks trees that are
staying. We had to work around those."
Faro and Lee Leavelle, senior construction
manager for the school district, both agreed that the lessons
learned in last year's project work in their favor.
"Everything is on schedule,"
said Leavelle. "Lathrop is doing a bang up job, their
second one for us. The lessons learned in the earlier project
are paying off now. We're very fortunate they won the bid."
Dave
Piper, project manager for Lathrop, confirmed that everything
is on plan and on budget. At press time, he said more than
half the buildings have been framed and infrastructure work
is continuing. The project site was formerly farmland, so
everything has to be installed - from sewer and water to utilities.
Cosumnes Oaks and Elizabeth Pinkerton is
the district's fourth version of the combined campus plan.
"It's one huge project," said Faro. "Twenty-seven
buildings in all, with separate classrooms and administrative
offices, plus a stadium, track and soccer field. The two schools
will share the library and performing arts center."
The two schools will be separated by fences
and gates.
The schools site is part of the Laguna
Ridge area. Under the city's Madeira Specific Plan, the 1,900
acres will eventually have 8,000 homes as well as a civic
center, office park, fire station, parks and retail. Currently,
Sparks, Nev.-based Reynen & Bardis Development is doing
infrastructure work on a couple of developments for Pulte
Homes and Morrison Homes.
However, with home construction slowing
down in Elk Grove, the school district put a halt to the Cosumnes
Oaks/Elizabeth Pinkerton originally scheduled opening of August
2007 in order for the housing - and new residents' children
- to catch up. Only 400 homes are expected to open by next
year. The new scheduled opening is fall 2008.
But the delay in opening is not affecting
the building plans, according to Lathrop's Piper. "We're
moving along and hoping to get much of the work done before
the rains start."
The Project Team
Owner: Elk Grove Unified
School District
General Contractor: Lathrop
Construction
Architect: Stafford King
Wiese
Major subcontractors: Bay
Cities Paving and Grading (earthwork, utilities, paving),
Concrete Services, Taylor Structures (wood framing for the
high school), McClone Construction (wood framing for the middle
school), Construction Specialties (plaster and gypboard),
Performance Contracting Inc. (acoustical ceilings) and Protech
General Contracting Services (erosion control/storm water
pollution prevention)
More September Newswatch
items...
Lessons Learned
Green Schools=Common
Sense
|