| Allergan R&D
3, Irvine
The
174,200-sq.-ft. research and development facility contains
a 50,000 sq. ft., an interstitial/utility level; two levels
of biology and chemistry research labs and an NMR lab with
support office space; a 250-seat auditorium; and site improvements.
The structural-steel frame is on spread footings/grade beams
with composite metal/concrete decks. The exterior wall consists
of EIFS, brick, metal panel and window wall systems. Equipment
additions and modifications were made to the existing central
utility plant. A 600-ft. utility trench, containing mechanical
piping services from the central utility plant to the building,
was installed, and a pedestrian bridge tying the "R&D
3" building with the existing "R&D 2" building
was erected.
Allergan hired Turner immediately after the A&E team
was selected so that Turner could contribute its expertise
in research and development buildings during preconstruction.
Turner performed extensive cost and constructability reviews
on all the major components of the building and its systems
to help deliver a contract price within the owner's budget
while meeting all of the space programming and quality goals.
The $51.7 million project's location-in the middle of a large
corporate campus-presented many challenges regarding the safety
of the owner's employees and the potential impact of the construction
to the day-to-day operations on the campus.
Turner effectively planned and implemented a safety and logistics
program that met these challenges. The construction of the
building was masked from the owner's employees with the use
of a unique wrap on the exterior of the building.
Midway through construction, the owner asked Turner to completed
the 250-seat auditorium earlier than originally planned. Turner
re-phased the construction schedule and delivered the auditorium
two months ahead of schedule, which let Allergan host a major
professional conference.
The Development Team
Owner: Allergan Inc.
Architect: MBT Architecture
General contractor: Turner Construction Co.
Engineers: M&E Engineer/Affiliated Engineers
Lab consultant: Earl Walls Associates
Key subcontractors:
Anderson & Howard Electric
Pan Pacific Plumbing
Stonhard (resinous flooring)
Return to the list
|