Projects
Top Projects 2008
Best of 2007
Best of 2008 Entry Info
Top 25 Highway Projects





Best of California 2004 Awards
Chumash Casino Resort, Phase 2, Santa Ynez
Chumash Casino Resort, Phase 2, Santa Ynez
Photo by Elizabeth Messina

Construction began on the $27 million second phase shortly after the opening of Chumash Casino Resort's first phase in 2003. The second phase included an 80,000-sq.-ft., 106-room hotel, pool, first-class spa, meeting and recreational facilities and a 427-space parking structure. The phase was completed 75 days ahead of schedule.

The Chumash Casino Resort was designed and built to generate revenue for the Santa Ynez Band of Chumash Indians.

The construction issues started with a confined, 4-acre site that greatly limited staging areas for cars, trucks and earthmoving equipment. The staging areas had to be moved as construction progressed.

"Everyone involved in the process-the general contractor, the architect, the design consultants and, most importantly, the owners-shared a teamwork philosophy that carried them throughout the entire process. Decisions were made effectively, costs were allocated fairly and deadlines were met on every phase of the project. In a few cases, certain aspects of the project were completed ahead of schedule."
-Steve Davis, principal in charge, Summit Architects Collaborative

The new 200,000-sq.-ft. facility includes a gaming area with table games and 2,000 slot machines, casino administration offices and five dining venues.

Since breaking ground in July 2002, the design/build project team-Perini Building Co., Thalden Boyd Architects and Summit Architects Collaborative-oversaw construction of the facility and finished three months ahead of schedule.

During the peak month, construction crews logged more than 57,000 man-hours. More than 9,000 people were involved in the building process, including fabricators, suppliers and craftsmen.

Additional challenges Perini managed to overcome included minimal disruption to casino patrons while constructing the hotel. Coordination and communication with the owner and operations were key issues in establishing traffic plans and site circulation. Perini also worked closely with public entities such as Caltrans and the California Highway Patrol to keep traffic situations minimal.

The Development Team

Owner: Santa Ynez Band of Chumash Indians
Owner's representative/construction manager: Summit Architects Collaborative
Architect: Thalden Boyd Architects
General contractor: Perini Building Co.
Engineers:
Curtain Wall Design and Consulting
Hunt Design Associates
ILA+Zammit Engineering Group
Independent Roofing/Waterproofing Consultants
Jessen-Wright Structural Engineers
Key subcontractors:
Alliance Roofing Co. Inc.
Bratton Masonry Inc.
Cupertino Electric Inc.
DC Vient Inc.
Door & Hardware Management Inc.
F. Rodgers Insulation Inc.
Fontana Steel
Granite Construction Co.
J&R Flooring Inc.
Keenan, Hopkins, Suder & Stowell Contractors Inc.
Meyer and Lundahl Manufacturing Co.
Morley Construction Co.
Orange County Erectors Inc.
Otis Elevator Co
Southland Industries

Return to the list

advertisement


 


Sponsors

© 2009 The McGraw-Hill Companies, Inc.
All Rights Reserved