|
Poway City Hall, Poway
The
new $20.4-million Poway City Hall consists of a 50,500-sq.-ft.,
two-story city administration building and a 6,000-sq.-ft.
council chambers building with a 129-seat community meeting
center. The project was phased over two years beginning in
October 2002. The city administration building was completed
in spring 2004. The council chambers opened in late fall of
2004, after demolition of the existing city hall and construction
of an open space park was complete.
The new city hall consolidates most of the city departments
under one roof-increasing productivity and centralizing services
for citizens. The innovative facility is designed to draw
in natural daylight and open spaces are featured throughout.
A new park and children's play area further enhance the site.
Designers infused Spanish with modern looks to evoke Poway's
"city in the country" sentiment. The use of slate
and exposed concrete effects give the building a modern feel,
while stucco, heavy timbers and deep-set windows are reminiscent
of the past.
The fusion of past and present can also be seen in the historical
trees and archeological Kumeyaay metate stone which were preserved,
stored and replaced after construction. In addition, a public
art program (a first for Poway) was developed specifically
for the building, which currently showcases Kumeyaay Indian
artifacts and art. The tragic loss of a 200-year old oak tree,
(due to disease, not related to the project) created further
opportunity to incorporate Poway's past into the future. Wood
from the historical oak, which graces the city's seal, was
used to fabricate several pieces of furniture in the building.
Challenges included constructing the new facility while sharing
a site and continuing operations with the old facility. This
was accomplished through creative phasing and site planning.
The phasing necessitated that some work such as the administration
center balcony had to be completed with extremely limited
laydown and delivery areas.
Rerouting of city employees and citizens conducting business
with the city was a daily challenge. A strong flow of communication
and signage were used to make pedestrian and vehicular traffic
safe and convenient during all stages of construction. Off-site
parking was utilized to allow space for material deliveries
and logistics. One specific example was the final-phase construction
of a large balcony on the new administration building. The
balcony was slated for construction in the final phase because
it would have impeded demolition of the old city hall, just
a few feet away. In a testament to superior site planning,
construction crews had just a 15-ft. corridor between the
newly completed City Hall and the partially constructed chamber
building in which to deliver supplies to construct the large
balcony structure. With little space for storage or maneuverability,
Barnhart managers meticulously scheduled deliveries to make
the best use of the space available. Deliveries were well-timed
and in concert with the project schedule.
Flexible and responsive scheduling was employed to maximize
site utility modifications. Communication with city staff
was critical to ensure limited disruption to city operations
and comfort of staff. Noise, safety and dust control plans
were top priorities of the Barnhart team. Working on the occupied
site necessitated extra planning to ensure important city
events and business were not disrupted due to noisy operations.
Coordination of site utility replacements was seamlessly scheduled
to avoid interfering with city staff business operations.
Services were disrupted in one-hour increments only when they
needed to be brought down.
Flexible scheduling was also essential when tragedy struck
San Diego County. The October 2003 wildfires reached just
1 mi. away from the site, creating hazardous atmospheric conditions.
Work had to be shut down for a week and new utility installations
were delayed up to four weeks while energy crews focused on
re-establishing power to those areas affected by damaged power
poles. Barnhart managers manipulated the already tight schedule
to accommodate this unforeseen challenge.
The construction management delivery system facilitated triumph
over these challenges by providing flexibility in the selection
of trade contractors as well as schedule and budget in an
effort to provide the city with an economical, high-quality
facility. This proactive approach allows Barnhart managers
to develop thoughtful and effective solutions to challenges,
and even develop modifications to overcome unforeseen conditions
and circumstances.
Owner's Comments:
"The old City Hall definitely
felt as though you were closed in tight corners, but the new
one is open and airy. And now we have state-of-the-art equipment."-Paolo
Romero, assistant to the city manager, Poway
Project Team:
Owner: City of Poway
Architect: McGraw/Baldwin Architects
Construction manager: Douglas E. Barnhart Inc.
Key subcontractors:
Able Heating & Air (HVAC)
Advance Plumbing
Gould Electric
E.F. Brady
J.P. Witherow (roofing)
Randy Rebar
Artimex Iron
Tower Glass
Vern Peltzer Plumbing
Nick Pecoraro Painting
Jaynes Corp.
Return to the list
|