|
Rebecca and John Moores Cancer Center,
La Jolla
The
$82-million Rebecca and John Moores UCSD Cancer Center, located
on UCSD's East Campus near Thornton Hospital, consolidates
outpatient services, research labs, clinical trials offices,
cancer prevention programs, community outreach activities
and more in a striking architectural addition to the campus.
Among its eye-catching architectural features are iridescent
stainless-steel shingles that change color as the day progresses,
a "flying bridge" stair in a three-story glass-fronted
atrium lobby, and an interior courtyard with mature stands
of bamboo, granite boulders, and a meandering dry creek bed.
The 270,000-sq.-ft. facility comprises two structures: a three-story
clinical service and administrative facility and a five-story
research tower.
The project proved challenging due to its complex design
and the scope of changes, many of which the client requested
during construction.
"The McCarthy team added value to this project by being
flexible and prepared to tackle any situation," said
Charles Kaminski, senior architect at UCSD. "For example,
when we decided to carve out a space from the existing construction
to add an MRI unit, McCarthy pulled out all the stops to meet
our requests and schedule constraints. McCarthy achieved the
goal successfully, against all odds."
Building the structural concrete shear walls for the lab
tower was also a challenge. The team had to develop special
concrete placing procedures to prevent concrete segregation
and cold joints.
Creating a space that was appealing to the public, patients,
and researchers proved challenging. One of the primary goals
of the project was to design the facility so that researchers
and clinicians all would be located in one central location,
thereby enhancing communication and interaction.
Another major challenge was integrating six different finishes
into the facility's exterior: stainless steel metal shingles,
plaster, metal panels, pre-cast concrete, stone, and curtain
wall. To ensure that all six finishes would be waterproof,
McCarthy built a complete exterior "mock-up" of
the skin systems to perform tests on each skin type. The design
team collaborated early in the project with the key skin subcontractors
to ensure the materials would perform as designed.
Despite zero-hour changes and numerous challenges, the project
team for McCarthy adhered to the original construction schedule,
with minimal impact on the overall time line and budget constraints.
Owner's Comments:
"McCarthy pulled out
all the stops to meet our requests and schedule constraints."
-Charles Kaminski, senior architect, UC San Diego
Project Team
Owner: UC San Diego
Architect: Zimmer Gunsul
Frasca Partnership
General contractor: McCarthy
Building Cos. Inc.
Engineering team :
Structural: KPFF Consulting
(Los Angeles)
MEP: Affiliated Engineers
W. Inc.
Civil: Pountney Consulting
Group Inc.
Key subcontractors:
Sierra Pacific West Inc.(site work)
McCarthy Building Cos. Inc. (cast-in-place concrete)
Bannister Steel Inc. (structural steel)
Center Glass Co.
Weiss Sheet Metal
Standard Drywall Inc.
Day Star Industries (millwork/casework)
R.M. Hasson (painting)
HPS Mechanical Inc. (plumbing)
A.O. Reed & Co. (HVAC)
Dynalectric Co.
Schmidt Fire Protection
ISEC Inc. (lab casework/equipment)
Return to the list
|