|
Sue and Bill Gross Women's Pavilion at
Hoag Memorial Hospital, Presbyterian, Newport Beach
A
comprehensive center combining progressive technology with
patient education and comfort, the Women's Center project
at Hoag Hospital entailed construction of a seven-level patient
tower plus a basement, an interstitial floor between the first
and second levels and a mechanical penthouse on an operational
medical campus.
An 11,000-sq.-ft., two-level connector building with a café
and gift shop was also constructed. The Women's Pavilion is
composed of a cast-in-place concrete mat slab foundation,
retaining walls and shear walls up to ground level with a
precast concrete and curtainwall exterior.
When the 320,000-sq.-ft. facility opened in October, it nearly
doubled the clinical space on the hospital's campus. It will
serve as the new main entrance for the hospital and will house
more than 15 new and existing services including women's health
services, ambulatory procedure services, laboratory services,
patient registration, patient education and a hospitality
center.
More than 1 million construction manhours and countless more
during design and preconstruction were spent to construct
this pioneering health care project. Located just 2 kilometers
away from the Newport-Inglewood Fault and expected to set
a precedent for future base isolated hospitals, the innovative
seismic technology on the Women's Pavilion presented unique
challenges. It is the first OSHPD building under construction
with a steel-moment frame on base isolators and the first
base-isolated hospital building under construction that had
the isolators tested for tension and shear.
Installing the base isolators meant temporarily supporting
4,000-lb. isolator base plates while concrete was poured into
forms containing the base isolator pads. Therefore, the base
isolator baseplates were bolted to the isolator pads and held
in place using a complex system of thread rods and wire to
ensure zero tolerance and avoid rework. Additionally, McCarthy
devised an elaborate template, allowing baseplates to be successfully
poured in 54 locations without a single failing.
"McCarthy understood the critical nature of the connection
between the columns and foundation with an isolator in between.
There was only 1/16-in. of tolerance to make it all fit together,"
said Randy Regier, AIA, president of Taylor & Associates
Architects.
The design documents required preheating of the building
frame's structural steel before welding could commence. A
precise welding plan was developed that eliminated the uncontrolled
effects of steel expansion and contraction that could be caused
by heating and cooling, thus throwing the building out of
plumb.
The tight site provided further challenges. An enormous crane
was needed to hoist 50,000-lb. structural steel columns and
to set a 20,000-lb. precast panel more than 300 ft. away.
After an appropriate location was found to accommodate this
crane, a pad was built and the ground was prepared to support
the crane and its loads.
"Although the challenges were many, we had a highly
efficient team, each of which brought their expertise and
ability to problem solve and to work together," said
Langston Trigg, vice president of facilities design and construction
at Hoag Hospital.
Owner's Comments:
"The entire team is proud
of its accomplishments. We beat our budget, finished ahead
of schedule and maintained a high level of quality in the
end product." -Langston Trigg, vice president of facilities
design and construction, Hoag Hospital
Project Team:
Owner: Hoag Memorial Hospital
Presbyterian
Architect, interior design: Taylor & Associates Architects
Construction manager: Jacobs Facilities Inc.
General contractor: McCarthy Building Cos. Inc.
Landscape architect: Rabben/Herman Design Office
Artwork consultant: J.D. Thompson & Associates
Intaglio artist: Tom Van Sant
Engineering team:
Taylor & Gaines (structural)
Tsuchiyama Kaino Sun & Carter (mechanical engineer)
R.E. Wall & Associates
(electrical engineer)
David A. Boyle Engineering (civil)
Key subcontractors:
Beck Steel (miscellaneous steel)
Briggs Electric
Control Air Conditioning
Coreslab Structures (precast concrete)
Cosco Fire Protection
CP Contractors (equipment installation OFCI)
Custom Metal Fabricators (expansion- joint cover assemblies)
DVV & Associates (exterior consultant)
Dynalectric
ETS Lindgren (MRI)
Herrick (structural steel)
ISEC (casework)
Johnson & Turner Painting
Letner Roofing
Malcolm Drilling
McCarthy Concrete
McIntyre (metal decking)
Model Glass
Mollenhauer (survey/field engineering)
Otis Elevator
Pan Pacific Plumbing
Performance Contracting Inc. (acoustic ceilings)
Premier Tile & Marble
Raymond (drywall/fireproofing)
Seeley Brothers (doors, frames, hardware)
Shaw & Sons (site concrete)
SMG Stone
Spectra Contract Flooring
Swisslog Translogic (pneumatic tube system)
Return to the list
|