|
Homer Avenue Caltrain Undercrossing, Palo
Alto
The
$4.5-million project consisted of the design and construction
of a new pedestrian/bicycle undercrossing (73-ft. long, 20-ft.
wide, and 9-ft. high) under Caltrain railroad tracks, approximately
800-ft. south of the Palo Alto Caltrain station. The undercrossing
is located between the Palo Alto Medical Foundation and the
Homer Avenue and Alma Street intersection. The undercrossing
provides access from the south of Forest Avenue residential
and commercial areas to the PAMF campus and to the Caltrain
station via the new bike path along Urban Lane.
The need for a new pedestrian/bicycle crossing of the railroad
tracks was identified during the review of the plan for the
new PAMF campus and SOFA Coordinated Area Plan Study. A feasibility
study for the pedestrian/bicycle crossing through the Caltrain
right-of-way was prepared. The study estimated the facility
would attract up to 1,800 users a day.
The undercrossing project involved relocation/lowering of
fiber optics along the railroad tracks, raising of the tracks,
secant pile drilling with cement deep soil mixing technology,
an open trench cut under the railroads, installation of pre-cast
and cast-in-place undercrossing structures, installation of
stairs and ADA compliant ramps at entry ways, installation
of a storm drain pump station, realignment of a 60-KV main
electrical line, and installation of new traffic signal at
Alma Street and Homer Avenue catering to pedestrian and bicyclist
traffic.
The project was fully funded by Transportation Equity Act
for the 21st Century, State Transportation Improvement Program
and other grant funds and local development fees.
The project was under expedited schedule with limited resources
and funding, according to the city. The project had to be
accelerated since the design and construction documents needed
to be complete within one year in order to start construction
in 2003 to meet deadlines to secure grant funding. No city
funds were available so project costs had to be covered by
grants and local development funds.
One of the major challenges for the project was coordinating
and obtaining approvals within schedule from agencies such
as Caltrans, Public Utility Commission, Peninsula Corridor
Joint Powers Board who controls the railroad tracks, and fiber
optics companies such as AT&T, Sprint and MCI Worldcom.
Approvals were also needed from the city entities like the
Architectural Review Board, Historical Review Board, Palo
Alto Bicycle Advisory Committee, and Building Department.
Due to State/Federal funding, the project had to follow strict
contracting, documentation and management procedures per Caltrans
requirements.
The project site was sensitive in nature as well. Since the
undercrossing was being constructed through the PCJBP easement,
the contractor, Anderson Pacific, had to work around railroads
servicing commute and freight trains 24 hours a day. Various
utilities were present along railroads such as fiber optics
and electrical main power lines which had to be relocated
and realigned. Relocations of utilities were tremendous tasks
by themselves. Any damage or downtime of the fiber lines could
have cost the city millions of dollars.
The construction method for the undercrossing was accomplished
by drilling soldier piles then open trench cut. Therefore,
majority of the construction for the structural frame was
done during nights and weekends when train services were at
minimal. The project site was in close proximity to commercial
and residential establishments, a hospital, and hotels, resulting
in noise sensitivity issues. Numerous outreach meetings and
programs were carried out to keep the neighbors informed.
Due to numerous other difficult facets of this project, the
project team encountered challenges in all directions during
the entire duration of the project. However, with the cooperation
from various agencies and diligence from project team members,
the undercrossing was built in budget and within schedule.
Judges' Comments:
- "This project went well
beyond just meeting the needs and responded to the community
in a thoughtful manner."
- The big plus for this project
is that it overcame so many difficulties within the community."
Project Team:
Owner: City of Palo Alto
Architect: Steven Grover Architects
Construction manager: TRS Consultants Inc.
Program manager: Palo Alto Public Works Engineering
General contractor: Anderson Pacific Engineering Construction
Inc.
Engineer: Nolte Associates Inc.
Return to the list
|